RE: H&W Football trophy and other stuff9 Jun 2023 12:25
Original RNS
01 June 2022
"Fabrication will take place at the Harland & Wolff Belfast site, with first steel being cut within approximately eight weeks' time. The programme schedule allows for four barges to be built in tandem, with the entire build programme ending around Q2 2023."
So, "ending around Q2", leaves a bit of wriggle room, I guess. ;)
16 February 2023 RNS
"The first major milestone for this contract has now been reached. The client has approved the hull and this will now pass into the painting hall prior to its delivery later in Q1 2023. The second barge will also soon be completed, whilst the next two are also well advanced. The work being undertaken on these barges has supported the facility in advancing vital shipyard skills which will be required for the Fleet Solid Support warship programme. Fabrication is now being conducted simultaneously on all barges throughout the production hall with numerous work stations set up and the project team tracking progress on a daily basis with the newly implemented IFS ERP Projects Module."
Second barge was deliverd last Friday. Four months later the next two that were "well advanced", only one looks like it's nearly ready. Unless there are hiding them somewhere else.
"simultaneously on all barges" might just be a bit of spin. imo
Guess they will have it nailed by the time they start on a proper ship.
Or should that be rivited. :)