The damage limitation continues.......PSEI next?Today 17:52
We've just had the 'first reveal' - acknowledgement of the existence of a 'concert party' - which begs obvious questions like 'Who else? , To what end? and 'How far back?
There's a lot of material to be mined (geddit?) from AT and MK's InvestorMeet disclosures, aka the'teach-in'.
MK .." After long due diligence processes with many other interested entities, RAM [Ed.: incorporated 19 Dec 2025] has now completed the technical, sovereign, and financial due diligence processes with our technical partners [Ed.: who they?], resulting in this transaction...."
AT.."We have to admit that the complexity of this transaction takes a bit of time to understand and wrap one’s head around...."
MK: .."We have shared these [workstreams] with our partners in the Republic of Congo — both at domestic and government levels — and our project partners [who are these partners???] and consultants [ditto] are ready to commence this work..."
MK:... “David — you asked whether the FEED and FID work programme could complete earlier than 18 months.
We would certainly like to. But these are required steps. Whether we were talking about this in 2019, 2023, or now in 2026, the work has to be undertaken in a certain way and takes a certain amount of time.
We have been working with the same project partners for 18 months...." [Ed.: ie Q2/Q3 2024].
The 6 May 2026 RNS (precursor to the latest fundraise) says
Workstreams now completed include:
· The confirmation of DRI product quality potential for both Stages;
· The completion of costing and feasibility of:
o modular hematite processing facilities ;
o thickened and dry tailings facilities for both Stages; and
o an optional single 30 Mtpa pipeline during Stage One (providing a COMPELLING alternative to the April 2026 case two-stage pipeline plan)*
· Update of specific project costs through an OEM enquiry process
· Assembly of a Constructor Engagement Programme for the Project.
* the presentation here is (deliberately?) misleading, since it downplays the economic difference.... and allows ZIOC to present a lower-than-expected 'new' NPV
The schedule can be recast as
Stage1 $M Stage2 $M
Twin Capex 637 1,343
Twin Opex 915 1,724
Total Twin 1,552 3,067
vs
Single Capex 986 986
Single Opex 659 774
Total Single 1,645 1,760
to show that a single pipeline SAVES $357M Capex at Stage2...and SAVES $950 M Opex.
''Big mistake'.
Key takeaways from the above:
- there's been a lot of technical, financial and sovereign engagement, behind the scenes, for a lot longer than previously presented;
- we've been working with the same partners and consultants since Q2/Q3 2024;
- the drop in NPV is a presentational choice.
Cont...