RE: Never ending nor beginning like an ever spinning plate14 Dec 2022 09:56
NEVERENDING DEVELOPMENT - 6 YEARS AND COUNTING !
31 March 2022
During the reporting period, the Group continued to develop its microCHP boiler, Marine engine and Waste Hear Recovery (WHR) applications and were also in discussions with a British certification company Enertek International Ltd
2 Nov 2021
Inspirit are in early-stage discussions with a view to entering into an agreement with a British certification company Enertek International Ltd. ("Enertek International")
32 March 2021
During the reporting period, the Group continued to develop its microCHP boiler
Specifically, the Company has spent time working to refine Inspirit's Stirling technology, reviewing the potential supply chain and detailing the product specifics
30 March 2020
During the period, the Group continued to advance its microCHP boiler and marine engine application with its European partners
29 Dec 2019
During the period, the Group continued to advance its microCHP boiler (the "Charger") closer towards the goal of commercialisation.
13 Nov 2019
Regarding the next stage in the manufacturing process of the 6.4kW mCHP with a 15kW thermal output boiler, the Company has continued with focusing on the improvements to the design of the Company's Inspirit Charger
29 March 2019
During the period, the Group has continued to advance its microCHP boiler closer towards the goal of commercialisation.
28 Dec 2018
During the year, the Group has continued to advance its microCHP boiler closer to towards the goal of commercialisation.
29 March 2018
The DFM process continues to yield several engineering improvements and manufacturing cost reductions whilst others are still expected.
Whilst this DFM process remains ongoing, the Group is now looking to proceed to the certification process
28 Dec 2017
During the year, the Group has been working to advance its microCHP boiler towards commercialisation.
The DFM process is the means by which the manufacturing cost of the technology is reduced through engineering improvements and through improved manufacturability. The DFM process has already yielded several engineering improvements and manufacturing cost reductions and more are expected
30 Dec 2016
This has been another progressive year for the Company where our mCHP boiler is getting closer to commercialisation