Less Ads, More Data, More Tools Register for FREE

Pin to quick picksTSG.L Regulatory News (TSG)

  • There is currently no data for TSG

Asacha Project Update

2 Mar 2011 07:00

RNS Number : 1365C
Trans-Siberian Gold PLC
02 March 2011
 

 

 

 

Trans-Siberian Gold plc

 

Asacha project update

 

 

London: 2 March 2011 - Trans-Siberian Gold plc ("TSG" or "the Company") (TSG.L)reports on the progress of construction at the Asacha site.

 

Underground mine development is continuing as planned. During January 2011 more than 130 metres and 1,500 m3 of mine development were completed. The ore stockpile at 31 January 2011 comprised more than 62,000 tonnes.

 

By mid February 2011, more than half of the plant building's internal concrete walls had been completed. The building's multi-layer roofing with thermal insulation was close to completion with 100% of the lower layer installed. Construction of ventilation and heating systems is underway. The coarse ore bin's concrete parts are also under construction. 

In spite of snowstorms and strong winds earthwork and geomembrane laying activities on the tailings storage facility have continued.

 

The thermally insulated repair shop building is ready, except for completion of its supply system, concrete floor and equipment foundations. Cold storage hangars have been completed and the sewage treatment facility awaits installation of its power supply, ventilation and heating. Construction of the site's water, heat supply and sewage networks is in progress. The powerline from the site's diesel generators to the mine has been completed. The license for cyanide storage has been granted and the facility commissioned.

 

As a result of a 30% increase in diesel fuel costs, additional soil replacement works for tailings storage and the water treatment pond and additional operating expenditure due to the extended construction period, the total capital cost of the Asacha project prior to commencement of production is now estimated at $128.5 million, net of $10.2 million VAT recoveries, compared to the September 2010 estimate of $124.5 million (net of $8.3 million VAT recoveries). The total project cost includes pre-commissioning mining and plant costs of $4 million, other pre-operating expenditure of $36.8 million, "first fill" equipment spares and consumables of $1 million and contingency of $0.6 million.

 

At a gold price of $850/oz, Life of mine ("LOM") cash costs on an all equity basis on total gold production of 590,000 oz are forecast at $218/oz, before taking account of a $17/oz credit from silver production (based on an assumed silver price of $10/oz). Cash costs including all royalties and taxes (in total $72.9 million, net of VAT recoveries), on an all equity basis are forecast at $342/oz. Total costs on the same basis, after depreciation of all capital expenditure (including $27.5 million post start up) and pre-start up mining and other operating expenditure, are forecast at $609/oz, giving a $241/oz margin at a gold price of $850/oz.

 

Actual expenditure on the project up to December 2010 amounted to $112 million, net of $7.7 million VAT recovered. The remaining costs prior to the commencement of production are estimated at $16.5 million, net of further VAT recoveries of $2.5 million, comprising:

 

 

 

$ million

Capital expenditure

Mine and mining equipment and facilities

1.1

 

Gold plant, site facilities and tailings storage (1st phase)

8.0

 

Off-site power supply and other infrastructure

2.7

 

Contingency

0.6

 

Total capital

12.4

Other costs

Pre-production mining, spares and consumables and other operating costs

6.6

 

 

19.0

Less VAT recoveries

 

2.5

 

 

16.5

 

 

A further $27.5 million of capital expenditure is expected to be incurred after the commencement of production (including $6.3 million on mine development, $5.1 million on the plant, tailings storage and solid waste landfill, $11.6 million for the completion of the external power line and $4.5 million contingency).

 

 

 

Ends

 

Contacts:

 

TSG

+44 (0) 1480 811871

Simon Olsen

 

 

 

Seymour Pierce Ltd

+44 (0) 207 107 8000

Stewart Dickson / David Foreman (Corporate Finance)

 

Jeremy Stephenson (Corporate Broking)

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCJBMRTMBJMBBB
Date   Source Headline
21st Feb 20067:01 amRNSAsacha Update
15th Feb 200611:02 amRNSHolding(s) in Company
14th Feb 20064:50 pmRNSMarket Maker Holding
14th Feb 20064:46 pmRNSMarket Maker Holding
14th Feb 20064:42 pmRNSMarket Maker Holding
10th Feb 20061:52 pmRNSHolding(s) in Company
8th Feb 200610:25 amRNSHolding(s) in Company
31st Jan 200610:24 amRNSHolding(s) in Company
19th Jan 200612:27 pmRNSHolding(s) in Company
9th Dec 200510:11 amRNSHolding(s) in Company
9th Nov 200511:06 amRNSDirectorate Change
17th Oct 20057:01 amRNSReview of Veduga strategy
21st Sep 20057:00 amRNSInterim Results
15th Sep 200512:41 pmRNSDirector Declaration
15th Sep 20057:01 amRNSDirectorate Change
1st Aug 20054:55 pmRNSAGM Statement
19th Jul 200512:11 pmRNSBlocklisting Interim Review
18th Jul 200512:12 pmRNSHolding(s) in Company
21st Jun 20053:15 pmRNSDirector Declaration
2nd Jun 20059:18 amRNSHolding(s) in Company
1st Jun 20059:52 amRNSSecond subscription completed
27th May 200511:07 amRNSEGM Statement
19th May 20057:01 amRNSDirectorate Change
11th May 20057:00 amRNSFinal Results
5th May 200511:47 amRNSHolding(s) in Company
4th May 20057:00 amRNSStatement re Asacha and EGM
28th Apr 20057:00 amRNSRe Agreement
18th Apr 20057:00 amRNSStatement re AGA subscription
4th Mar 20059:29 amRNSHolding(s) in Company
3rd Mar 20057:01 amRNSDrilling Report
2nd Mar 20058:15 amRNSHolding(s) in Company
23rd Feb 200511:26 amRNSHolding(s) in Company
14th Jan 20051:57 pmRNSBlocklisting Interim Review

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.