RE: Decline & PFS25 Oct 2020 09:38
The MRE will basically support a Scoping Study as defined below.
38. A Scoping Study is an order of magnitude technical and economic study of the potential viability
of Mineral Resources. It includes appropriate assessments of realistically assumed Modifying
Factors together with any other relevant operational factors that are necessary to demonstrate at
the time of reporting that progress to a Pre-Feasibility Study can be reasonably justified.
A Scoping Study must not be used as the basis for estimation of Ore Reserves.
If the outcome of a Scoping Study is partially supported by Inferred Mineral Resources and/or an
Exploration Target, the Public Report must state both the proportion and relative sequencing of the
Inferred Mineral Resources and/or an Exploration Target within the Scoping Study
The PFS will support an actual Ore Reserve.
39. A Preliminary Feasibility Study (Pre-Feasibility Study) is a comprehensive study of a range of
options for the technical and economic viability of a mineral project that has advanced to a stage
where a preferred mining method, in the case of underground mining, or the pit configuration, in
the case of an open pit, is established and an effective method of mineral processing is determined.
It includes a financial analysis based on reasonable assumptions on the Modifying Factors and
the evaluation of any other relevant factors which are sufficient for a Competent Person, acting
reasonably, to determine if all or part of the Mineral Resources may be converted to an Ore
Reserve at the time of reporting. A Pre-Feasibility Study is at a lower confidence level than a
Feasibility Study