RE: Tanzania tasks TPDC to ensure the timely completion of all oil and gas projects15 Mar 2026 14:49
Also worth reminding again of this from last week’s article:
‘Makame also mentioned another project involving the drilling of wells in the Ruvuma (Ntorya) Block and construction of a raw gas pipeline from Ntorya to Madimba in Mtwara Region, which consists of two components: upstream and midstream.
‘He explained that the upstream component includes drilling a new well (Chikumbi-1), rehabilitation of one well (Ntorya-1) and production testing of another well (Ntorya-2), noting that its completion will increase natural gas production by about 60 million cubic feet.
‘“The project is estimated to cost approximately USD 23.5 million. Currently, it is at the stage of procuring drilling services for the Chikumbi-1 well, site clearance for drilling activities and the final stages of the Environmental and Social Impact Assessment (ESIA),” he said.’