RE: Mill Working11 Oct 2023 23:35
Yes you're right material being fed in consistently, but unfortunately in this operation it's not about what goes in it's about what comes out and right now it's not SC6, when or if SC6 comes out of the back end is yet to be determined . Realistic nameplate of 125%, that's a theoretical possibility nothing more. Handover in Q1 yes if they get the new mill delivered and installed. The last two are likely months away if they'll happen at all. What's of concern is the ability to produce SC6 or SC5.5 that's what makes PREM any money and as it stands the plant needs further modifications and testing to determine if that's possible. Reality check folks, nothings changed other than a mill is now milling material that's feeding a plant that's still not producing spod of a saleable grade