28th May RNS
An on-site processing plant is being planned, with funding discussions ongoing, for the low-grade ROM that incorporates a copper leaching, solid liquid separation, and copper precipitation circuit. Implementation of two 60 tonnes per hour (tph) processing units (30 000 tpm per unit) are targeted with a combined production capability of 350tpm of Cu units. Implementation of the second unit is scheduled to follow approximately six months after the trials on the first unit.
Extended pilot trials are scheduled over the coming three months to include the copper precipitation processing step to confirm the optimal composition of the copper precipitant for direct refining at Sable. The implementation of the first copper processing unit at Munkoyo is targeted for commissioning by end of Q1 CY2026.