NPV Model12 May 2020 21:08
Ran some numbers through NPV model - ore body 156MT, throughput 15.5MT pa, grades Au 2.5g/t, 0.45% Cu, discount rate 9%, Au $1750, Cu $5000, 11 yr mine life, 4 yr mine lead time, Au & Cu recovery at 0.85%, AISC $996 / oz prod (excluding by-product credits, ignoring all other credits), shares 4,353,607,171 (incl warrants, options, shares to Pacific Trends), 1.25 $>£
Got 28p per share for 30% Hav, but was after comments on Au/Cu grades, ore body size used etc. I'm still working off 60,000m² x 900m depth - is that still good or bigger now? Is Telfer throughput at 15.5Mtpa too low?
Thanks and GLA.
C