RE: Hav & Telfer Production Figures15 Aug 2025 19:32
From Aprils reserve report:-
“The Havieron base case demonstrated a compelling multi-decade Havieron mine plan, for:
§ Havieron to operate with a steady state mining throughput rate of 2.8Mtpa and average grade processed of 2.74g/t Au and 0.32% Cu;
§ Havieron ore to be processed through the Telfer processing facility, with utilisation of a single processing train through Telfer's Train 1 circuit at 750t/h, on a campaign basis at approximately 50% utilisation;
§ Havieron to produce on average 221koz Au annually during steady state operations, first 15 years;
§ a steady state operational period of 15 years, total mine life of 20 years, and total processing period of 19 years;”