In a Nutshell - Now, Soon & Later14 Jul 2022 21:54
Updated summary adapted from recent posts, RNSs & debate on this BB:
Kenya:
> KIlimapesa mine = 100% owned working mine 1koz/month Q1/2 to 2koz/month by end Q4 Dec-22
> Kilimapesa MRE (Batch 1&2 infill) = 566koz RNS @12-Jul-22 so 10 year LoM @target 24koz production
> Kilimapesa MRE (Batch 3&4 Expansion) = Target for Oct-22 so expecting considerable new resources to added
> Red Ray MRE = 140koz JORC ... await addition to exploration licences
> Drill Programme = Batches 1, 2 & 3 complete and #4 expansion underway at $300k/month cost
Tanzania:
> Nyakafuru project = 'mine ready' 658koz MRE based on open pit & CIL processing ... await plan & funding in Q3/4
> NYakafuru Reefs = 400k 'Add-On' project ... await acquisition confirmation
Production - extensive upgrades:
1) Mine to expand ore production - added extra stopes underground and open pit at KIlimapesa
2) Process Plant existing & new capacity:
> Plant 1 = existing 15ktpm Traditional screen> Mill> Grind> Gravity separation & CIL processing
> Plant 2 = existing 5ktpm Tailings CIL processing plant fed by Plant 1
> Plant 3 Small Heap Leach (4x 5kt pads) = newly built, commissioning and in production Q2'22
> Plant 4 HUGE Heap Leach (2x 60kt pads) = build underway Q2/3'22
3) Process Plant - upgrading capacity & %recovery improvements in Q1/2'23
> Plant 1&2 = existing 15ktpm plant to be upgraded to 30ktpm
Kilimapesa anticipated production - based on Q1 Operations Report RNS 20-May-22 & latest presentation:
Q2'22 = max 1,097oz/month from Plants 1 & 2 only "possible" vs. 900oz "best guess" & bit more with some HL
Q3'22 = max 1,689oz/month from Plants 1, 2 & 3 only "possible" vs. 1,200oz "best guess"
Q4'22 = max 1,689oz/month from Plants 1, 2 & 3 only "possible" vs. 1,500oz "best guess"
Dec-22 = max 2,577oz/month from Plants 1, 2, 3 & 4 (0.5x 60kt pad) only "possible" vs. 2,000oz "best guess"
Note: Assumes Heap Leach is 1 month cook cycle & plant 4 partial production
Bottom Line Finances assuming steady State 2koz/month from Dec-22:
Using RM stated AISC $1,250 then Kilimapesa kicks out high FCF using POG=$1,800:
Dec-22 = 2koz*(1,800-1,250) = $1,100k or £913k minimum/month
> Annual Revenue = $43.2m or £36.3m at 24koz/annum production
> Annual Free cashflow = $13.2m or £11m at POG=$1,800 & AISC =$1,250
Kilimapesa Fully built-out & upgraded operation from Q2/3-2023 = 4koz/month
Plant 1&2 = 30kt *(2.5g/t *0.91)/31.1 = 2,180oz ... assume 20day/month operation & 91% recovery
Plant 3 (4x 5kt pads) = 20kt /3m *(1.72g/t *0.70)/31.1 =260oz (see Note)
Plant 4 (2x 60kt pads) = 120kt /3m *(1.72g/t *0.70)/31.1 = 1,560oz (see Note)
Note: uses Q1'22 achieved grades & HL recovery improved 52.5% to 70% (best guess) on 3-month cook cycle
IMHO route to Dec-22 @2Koz/month & 4koz/month in Q3/4-23 needs no new CAPEX, but switch HL cycle from 1 to 3-month cook cycle as implied by latest presentation. Gold production will be 2-3koz in Q1/2'23 due to Plant 1&2 upgrades.
ATB APR