The latest Investing Matters Podcast with Jean Roche, Co-Manager of Schroder UK Mid Cap Investment Trust has just been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksTSG.L Regulatory News (TSG)

  • There is currently no data for TSG

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Project Update

22 May 2008 07:00

RNS Number : 0073V
Trans-Siberian Gold PLC
22 May 2008
 



Trans-Siberian Gold plc

Asacha Project update

LONDON: 22 May 2008 - Trans-Siberian Gold plc ("TSG" or "the Company") (TSG.L) reportthat it has undertaken a comprehensive review of the scope, costs and economics of its Asacha project over the past eight months. The review took longer than anticipated due to the need for extensive investigations into plant foundation requirements in this seismically active location and the need to supply grid power instead of relying on diesel power generation as previously planned to avoid the latter's increasingly high costs and supply risksAccess to grid power has proven feasible with very significant operating cost savings, albeit at the expense of a slower build up to full production, with the originally planned annual throughput of 200,000 tonnes of ore now expected to be achieved in 2011.

During the review period detailed design work has continued, mining of the main development access adit has commenced, the accommodation camp has been substantially completed after modification and earthworks and foundation work are also in progress.

The total project cost until Asacha is cash flow positive is now estimated at US$105.6 million, net of US$6.3 million VAT recoveries, compared to the September 2007 estimate of US$101.2 million (net of VAT recoveries of US$3.2 million). The total project cost includes pre-commissioning mining costs of US$5.0 million, other pre-start up operating expenditure of US$23.6 million and contingency of US$4.0 millionUS$58.3 million, net of US$1.4 million VAT recovered, has been spent up to the end of April 2008.

The US$4.7 million increase in pre-start up capital expenditure from the September 2007 estimate includes a net increase of US$3.5 million for the provision of external power supply. Other capital cost increases have been partially offset by savings in a number of areas, principally through the use of own labour and equipment for a major part of the infrastructure and tailings dam construction.

Projected operating costs have also been substantially reduced. At a gold price of US$750/oz, Life of mine ("LOM") cash costs on an all equity basis on total gold production of 590,000 oz are forecast at US$200/oz, before taking account of a US$32/oz credit from silver production. Cash costs including all royalties and taxes (in total US$70.9 million, net of VAT recoveries) on an all equity basis are forecast at US$320/oz. Total costs on the same basisafter depreciation of all capital expenditure (including US$10.5 million post start up) and pre-start up mining and other operating expenditure, are forecast at US$514/oz.

Mine output is expected to increase from 70,000 mt of ore in 2009 to 150,000 mt in 2010 and 200,000 mt in 2011, with gold production of 12,000 oz in 2009, 56,000 oz in 2010 and 68,000 oz in 2011. Based on the current JORC resource, operations would continue thereafter at that level for four and a half years, with annual production increasing to between 95,000 oz and 111,000 oz due to higher grades. However it is expected that overall exploitable reserves will be increased by at least 50% from the 590,000 ounces assumed in the current feasibility study, principally from the northern extension to the main orebody. Exploration also continues at Rodnikova where the JORC resource currently comprises 166,000 ounces in the indicated category and an additional 238,000 ounces inferred.

The projected return of the Asacha project on an all equity basis at a gold price of US$750/oz is over 20% and close to 50% when expenditure to date is excluded.

TSG reported on 25 February 2008 that the previously reported increase in the interest of UFG Asset Management ("UFG") and its associates to 32.96% of the Company's shares constituted an Event of Change of Control ("ECC") in respect of the US$10 million loan provided to TSG by AngloGold Ashanti Limited ("AGA") in June 2006 (the "AGA loan") The AGA loan had been repayable in equal tranches, on the first and second anniversaries of the commencement of gold production at Asacha, and was convertible into TSG shares when the Company raised new equity, however as a result of the ECC the capital and accrued interest of the loan became immediately due and payable. TSG has repaid US$4 million and accrued interest, in total US$5.7 million, in accordance with an agreed payment schedule, in line with the Company's maturing cash deposits.

The Group's total requirement for additional funds before the Asacha mine is cash flow positive, including further exploration at Rodnikova, corporate costs and the purchase of the remaining 4.98% minority interest in Asacha is US$50 million. 

Discussions are in progress with Russian banks in respect of project finance of US$25/30 million. TSG also plans to raise up to US$25 million of new equity through a placing during the next two months. UFG has indicated that it is prepared to subscribe for a minimum of US$10 million of this new equity.

The Asacha licence requires TSG to bring the Asacha mining enterprise into operation at its projected capacity in accordance with the technical design at a rate of not less than 1,000 kg of gold per annum before the end of 2008. Although it is now expected that the Asacha plant will only be commissioned in the third quarter of 2009, due to the delays in resolving the power issue, the mine will be operating at a rate commensurate with the minimum capacity required by the end of 2008. The Companbelieves that it is operating in full compliance with the license agreement.

The TSG Board believes that, after many setbacks and disappointments, the Company is now on course to complete the necessary funding over the next few months and start commercial production in 2009, with the financial prospects based on currently projected gold prices better than they have ever been.

Ends

Contacts:

TSG

Simon Olsen   +44 (0) 1223 265760

Seymour Pierce

Stuart Lane  +44 (0) 20 7107 8000

Geological information in this report is based on data reviewed by Mr V Zhouravlev, Chief Geologist of OOO Trans-Siberian Gold Management who is an expert of the GKZ (State Reserves Commission of the Russian Federation) with 45 years relevant experience in mineral exploration and a Qualified Person under AIM rules. Mr Zhouravlev consents to the inclusion of the information in the form and context in which it appears.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEAFIFSASEEI
Date   Source Headline
21st Feb 20067:01 amRNSAsacha Update
15th Feb 200611:02 amRNSHolding(s) in Company
14th Feb 20064:50 pmRNSMarket Maker Holding
14th Feb 20064:46 pmRNSMarket Maker Holding
14th Feb 20064:42 pmRNSMarket Maker Holding
10th Feb 20061:52 pmRNSHolding(s) in Company
8th Feb 200610:25 amRNSHolding(s) in Company
31st Jan 200610:24 amRNSHolding(s) in Company
19th Jan 200612:27 pmRNSHolding(s) in Company
9th Dec 200510:11 amRNSHolding(s) in Company
9th Nov 200511:06 amRNSDirectorate Change
17th Oct 20057:01 amRNSReview of Veduga strategy
21st Sep 20057:00 amRNSInterim Results
15th Sep 200512:41 pmRNSDirector Declaration
15th Sep 20057:01 amRNSDirectorate Change
1st Aug 20054:55 pmRNSAGM Statement
19th Jul 200512:11 pmRNSBlocklisting Interim Review
18th Jul 200512:12 pmRNSHolding(s) in Company
21st Jun 20053:15 pmRNSDirector Declaration
2nd Jun 20059:18 amRNSHolding(s) in Company
1st Jun 20059:52 amRNSSecond subscription completed
27th May 200511:07 amRNSEGM Statement
19th May 20057:01 amRNSDirectorate Change
11th May 20057:00 amRNSFinal Results
5th May 200511:47 amRNSHolding(s) in Company
4th May 20057:00 amRNSStatement re Asacha and EGM
28th Apr 20057:00 amRNSRe Agreement
18th Apr 20057:00 amRNSStatement re AGA subscription
4th Mar 20059:29 amRNSHolding(s) in Company
3rd Mar 20057:01 amRNSDrilling Report
2nd Mar 20058:15 amRNSHolding(s) in Company
23rd Feb 200511:26 amRNSHolding(s) in Company
14th Jan 20051:57 pmRNSBlocklisting Interim Review

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.