22 May 2008 07:00
๏ปฟ
Trans-Siberian Gold plc
Asacha Project update
LONDON:ย 22ย Mayย 2008ย -ย Trans-Siberian Gold plc ("TSG" or "the Company") (TSG.L) reportsย thatย it has undertakenย a comprehensive review of the scope, costs and economics of its Asacha project over the past eight months. The review took longer than anticipated due to the need for extensive investigations into plant foundation requirements in this seismically active location and the need to supply grid powerย insteadย ofย relying onย diesel power generation as previously plannedย to avoid the latter's increasingly high costs and supply risks.ย Access to grid powerย has proven feasible with very significant operating cost savings, albeit at the expense of a slower build up to full production, with the originally planned annual throughput of 200,000 tonnes of ore now expectedย to be achievedย in 2011.
During the review period detailed design work has continued,ย mining of the main development access adit has commenced, the accommodation camp has been substantially completed after modification and earthworks and foundation workย areย also in progress.
The total project cost until Asacha is cash flow positive is now estimated at US$105.6ย million,ย net of US$6.3 million VAT recoveries, compared to the September 2007 estimate of US$101.2ย millionย (net of VAT recoveries of US$3.2 million). The total project costย includesย pre-commissioningย mining costs of US$5.0 million, other pre-start upย operating expenditure of US$23.6ย million and contingency of US$4.0ย million.ย US$58.3ย million, net of US$1.4 million VAT recovered,ย hasย been spentย up toย the end ofย Aprilย 2008.
The US$4.7ย millionย increase inย pre-start upย capital expenditureย from the September 2007 estimate includes a net increase of US$3.5 million forย the provision of externalย powerย supply. Other capital cost increases haveย been partially offset byย savings in a number of areas, principally through the use of own labour and equipment for a major part of the infrastructure and tailings dam construction.
Projected operating costs have also been substantially reduced.ย At a gold price of US$750/oz,ย Life of mine ("LOM") cash costsย on an all equity basis on total gold production of 590,000 oz are forecast at US$200/oz, before taking account of a US$32/oz credit from silver production. Cash costsย including allย royalties andย taxesย (in total US$70.9ย million, net of VAT recoveries) on an all equity basisย are forecast at US$320/oz. Total costsย on the same basis,ย afterย depreciationย of all capital expenditure (including US$10.5ย million post start up) andย pre-start up mining and otherย operatingย expenditure,ย are forecast at US$514/oz.
Mine outputย is expected toย increaseย from 70,000 mt of ore in 2009ย toย 150,000 mt in 2010ย andย 200,000 mt in 2011, with gold production of 12,000 oz in 2009, 56,000 oz in 2010 and 68,000ย ozย in 2011. Based on the current JORC resource, operationsย would continue thereafter at that level forย four and a halfย years,ย with annual production increasing toย betweenย 95,000 ozย and 111,000 ozย due to higher grades.ย Howeverย it is expected that overall exploitable reserves will be increased by at least 50% from theย 590,000ย ounces assumed in the current feasibility study, principally from the northern extension to the main orebody. Exploration also continues at Rodnikova where the JORC resource currently comprises 166,000 ounces in the indicated category and an additional 238,000 ounces inferred.
The projected return of the Asacha project on an all equity basis at a gold price of US$750/oz is over 20% and close to 50% when expenditure to date is excluded.
TSG reported onย 25ย February 2008ย thatย the previously reported increase in the interest ofย UFG Asset Management ("UFG")ย and its associatesย to 32.96% of the Company's shares constituted an Event of Change of Control ("ECC")ย in respect of theย US$10 million loan provided to TSG by AngloGold Ashanti Limited ("AGA") in June 2006ย (the "AGA loan")ย Theย AGAย loanย had beenย repayable in equal tranches, on the first and second anniversaries of the commencement of gold production at Asacha, andย wasย convertible into TSG shares when the Company raisedย new equity, howeverย as a resultย of the ECC the capital and accrued interest of the loanย became immediatelyย due and payable. TSGย has repaid US$4 million and accrued interest, in total US$5.7 million,ย in accordance with anย agreedย payment schedule, in line with the Company's maturing cash deposits.
The Group's total requirement for additional funds before the Asacha mine is cash flow positive,ย includingย further exploration at Rodnikova, corporate costs and the purchase of the remaining 4.98% minority interest in Asacha is US$50ย million.ย
Discussions are in progress with Russian banks in respect of project finance of US$25/30 million. TSG also plans to raiseย up to US$25 million of new equity through a placing during the next two months.ย UFG has indicated that it is prepared to subscribe for a minimum of US$10 million of this new equity.
The Asacha licence requiresย TSG toย bring the Asacha mining enterprise into operation at its projected capacity in accordance with the technical designย at a rateย of not less thanย 1,000 kg of goldย per annumย before the end of 2008.ย Although it is now expected that the Asacha plant will only be commissioned in the third quarter of 2009, due to the delays in resolving the power issue, the mine will be operating at a rate commensurate with the minimum capacity required by the end of 2008. The Companyย believes that it is operating in full compliance with the license agreement.
The TSG Board believes that, after many setbacks and disappointments, the Company is now on courseย to complete the necessary funding over the next few months and start commercial production in 2009, with the financial prospects based on currently projected gold prices better than they have ever been.
Ends
Contacts:
TSG
Simon Olsenย ย +44 (0)ย 1223ย 265760
Seymourย Pierce
Stuart Lane ย +44 (0) 20ย 7107 8000
Geological information in this report is based on data reviewed by Mr V Zhouravlev, Chief Geologist of OOO Trans-Siberian Gold Management who is an expert of the GKZ (State Reserves Commission of theย Russian Federation) with 45 years relevant experience in mineral exploration and a Qualified Person under AIM rules. Mr Zhouravlev consents to the inclusion of the information in the form and context in which it appears.
Follow the stocks