RE: I3E Financing and Misconceptions24 Oct 2019 11:25
BBN,
Thank you for the response and I stand corrected - indeed 120 days is now the current schedule. However, I do have a couple of doubts / questions:
1) $41m was referenced in 10th Jan 19 RNS which presumable formed the basis of the funding plan - no scheduled referenced.
2) April RNS stated a 94 day program no cost referenced
3) You have highlighted the 120 day plan sent to the OGS - what date was this filed ? If this was after April then it is not clear at all what the basis of $41m is. Logical assumption would be 94 days with contingency on top .
4) I ran some numbers based on $41M, 94 day plan, 15% contingency, 115 day forecast along with some other assumptions on standby rate and fixed / other one off costs. I calculate after deducting the $3M deferred payment a total cost of about $38M, This excludes G&A, finance costs and other potential commitments due such as LLI. Still shows a little leg room but not as much as your estimate assuming there are no significant additional costs.
5) Who is Redmires by the way ?