News flow and patience24 Jan 2019 08:26
Cracking RNS, it’s still going to take a bit of patience though.
CPR March?
We have ongoing HH planning application which could take 3-9 months from dec18.
Arreton3 application will be submitted in the next 10 weeks and take 16-26 weeks to go to council
Godley Bridge 10 weeks to submit 16-26 weeks (maybe longer , it’s surrey!)
HH2 rig arrives spring... March April?
HH1z March April ?
Arreton South planning submit April -May , then 16-26 weeks to council
Broadford Bridge sidetrack planning needs to be submitted June-July for drill Jan 2020?
The UKOG planning teams will be extremely busy..