RE: Lincoln Well3 Jul 2020 08:47
Hi Yobbo,
From an article earlier this year:
“ The JV is,
therefore, seeking a field determination at Lincoln to progress towards field
development incorporating a single well tie back to the Aoka Mizu of either the
Lincoln Crestal well or an alternative shallower producer.
Based on
existing consents, the Lincoln Crestal well is planned to be plugged and
abandoned later this year. The suspension consent, which sets the deadline for
this activity, has been extended from 22 June 2020 to 30 September 2020 due to
the ongoing COVID-19 pandemic.
This extension
also allows Hurricane to gather additional long-term pressure data, expected to
provide further insight into the dynamic behaviour of the Lincoln reservoir.
The Transocean Paul B. Loyd Jr. semi-submersible rig, which is still under contract with Hurricane, is currently stationed in the Cromarty Firth and is expected to carry out this activity, but it is noteworthy that the JV is looking into alternative rig options.”