Planning progress at a snails pace.23 May 2022 12:20
Another submission from the council re planning application. So those that don't believe Peel are putting the effort into the site the following is a copy of the latest request for answers.
On Behalf Of: Environmental Protection Team
Comments
Further to comments made on 10 May 2022 with respect to land contamination, Environmental Protection also add the following:
It is noted that the application red line boundary is larger than the site boundary presented in the submitted report (Smith Grant LLP, Stage 1 Geo-Environmental Assessment. Proposed Protos Plastic Park: Sites 9B, 10A, 11 and 12 located off Grinsome Road / Marsh Lane, Ince, Cheshire. Dated September 2021. Reference. R2997-R01-v3 Final).
Specifically, there is a strip of land to the west of Site 9B, associated with what is understood to be a hydrogen pipeline route.
Whilst this area is likely low risk with respect to contamination, this part of the site must be included in the site assessment and conceptual site model to fully assess potential risks.
Therefore, a revised preliminary risk assessment, taking into account the full site boundary, is required. All other future report submissions should also take this area into account.
Environmental Protection recommend the following revised conditions are attached to any decision notice if planning approval is granted.
Contaminated Land
1. No development shall take place until the following components (a to d) of a structured scheme to deal with the risks associated with actual or potential contamination of the site have each been submitted to and approved in writing by the Local Planning Authority (LPA):
a. A preliminary risk assessment which identifies:
- all previous uses on or within influencing distance of the site
- potential contaminants associated with those uses
- a conceptual model indicating the sources, pathways and receptors of contamination
- actual or potentially unacceptable risks arising from contamination.
- initial remediation options.
b. A detailed scheme of site investigation based on component (a) from which a detailed assessment of risk to all current and future receptors that may be affected, including those off site, will be derived.
c. A remediation options appraisal and implementation strategy, based on the detailed results of (b), giving full details of the remediation measures required and how they are to be undertaken.
d. A verification plan providing details of the data that will be collected in order to demonstrate that the remediation works set out in (c) are complete and effective and identifying any requirements for longer-term: - monitoring of pollutant linkages; maintenance, contingency actions and reporting.
The pre-development structured scheme shall be implemented as approved unless revision is agreed with the LPA in writing.
End of part 1