Protos Timeline for PHE build26 May 2022 11:14
Just to remind everyone again the following is still on track even with NAT ENGLANDs interference. We are still in spring until the 21st June or so google states. Personally the key points I want to see is the build not starting any later than the 31st of August deadline for repayment of the loan to SPV and peels confirmation to be sole seller of DMG process for the first 10 plastic parks. Even if planning permission runs into the early summer I still want to see a shovel in the ground by the 31st of August 2022.
Protos at Ellesmere Port, Cheshire (Part of Peel NRE)
- Design & development of a local CO2 network will continue to enable emitters at Protos who capture their emissions to transport their CO2 to the HyNet pipeline which will be developed adjacent to Protos. This will further contribute to reducing emissions at Protos and delivering net zero in the North West. Completion expected by end 2025.
- Feb/March– completion of the Protos Grid substations to import and export electricity at Protos to the regional grid. This will also give Protos the ability to provide power to occupiers at Protos. This will enable 50MW of export capacity and 6MW of import. Full export of 124MW and 57MW import due October 2023. (Completed as far as I can see)
- Spring - planning decision expected to bring the first Plastic Park to the UK to process some of the 4.9 million tonnes of plastic waste produced in the country each year.
- Summer/autumn - start on site at the plastic-to-hydrogen facility to turn unrecyclable plastic waste in the region into a clean fuel for buses, HGVs and cars. (31st August Deadline)
- Autumn – completion of three further ecology areas providing habitat for wading and overwintering birds and water voles. This brings the total area dedicated to flora and fauna at Protos to over 45 hectares, the equivalent of 45 rugby pitches.
- By summer – completion of phase 2 infrastructure works including approx. 1.6km of roads, bridges, drainage and ecology areas to facilitate future plot development on site.
So gentlemen have a bit more patience and fill your boots with low priced shares.
MJA