Are we there yet?18 Nov 2022 02:26
Part 1 - Background analysis.
I have done this brief analysis for my own info, perhaps others might also find it helpful, especially in the light of diverging, and often unreferenced, views that have been expressed here over the last few days.
AJ-1 well (1988).
This found oil in the Lower Cretaceous Lacustrine sequence. This sequence included pebbly, partially unconsolidated sands (reservoirs), interleaved with clays and siltstones. This sequence was about 340m thick, with a net pay of about 120m. The drilling encountered problems - the pebbly unconsolidated sand was difficult to drill, causing nutation of the bit, with resultant side wall erosion worsened by drilling mud wash out, and the clay sequences expanded into the bore under pressure from above. The drill string broke, they were unable to recover it, and had to sidetrack. A summary of this is found on pp. 88-91 of the 20th March 2022 Strand Hanson CPR.
Gazania-1 plan.
This drill was planned to penetrate the same stratigraphic target as AJ-1, but up-dip and therefore at a shallower level (-3000m for AJ-1, -2200m for GA-1. This is designated the Gazania prospect. GA-1 is also targeting a shallower target, Namaqualand, which is deltaic/lacustrine, but is assumed to have the same lithology as the AJ-1 Lacustrine sequence. For this reason, both Gazania & Namaqualand prospects are likely to present the same potential drilling problems as AJ-1. If successful, the intent was to sidetrack through a fault into the Pelargonium prospect. Pelargonium is exactly the same sequence as Gazania, but about 100m shallower, since Gazania is downthrown relative to Pelargonium.
There is some variance of opinion as to how long the initial (Namaqualand + Gazania) drill would take. The CPR states 20 days - p.85. Gil has stated 25 days in various interviews. p.14 of the 2018 Africa Energy presentation gives a very useful detailed drill plan (plus expected stratigraphic column) giving 30 days.
I have not seen a plan for the Pelargonium sidetrack, nor an estimate of how long it would take (anyone have a reliable reference?). If the original idea was to re-visit the Namaqualand sequence on the way down, they would have to ST at around -1800m (see diagram, CPR p.92), and go down through the Pelargonium fault block to around -2400m, giving perhaps a maximum of 700m. Since we now have a delay, they may be considering a less ambitious sidetrack, just targeting Pelargonium - this would only need to start at -2000m, so would be 200m, or two days, shorter. Two bores through Namaqualand might give some data on lateral pinch-out of reservoirs, but this may be of limited use since they are so close together, but most importantly would of course give another chance for the drill to stick/break.
We know from Keith Hill's comments that there was an initial weather delay (presumably from 4th to 9th Oct), followed by 10-15 days further delay while drilling. Running out of space, so conclusions