RE: Should have news this week and ....3 Nov 2019 18:34
Hello Lucky,
I think I am with Andrew on this one.
Having placed letters of intent and paid deposits for long lead time items does not, in itself, guarantee that CIL processing will start on schedule. We have seen far too many schedules slip over the last few years to be able to take that for granted.
However, if memory serves, initial hard rock processing was intended to start in Q4, using existing gravity processing equipment and that does not rely on CIL availability.
Hard rock production is, by it's very nature, more reliable than alluvial production so I will be a lot more confident once gravity processing has commenced as that will then fill the gap whilst the CIL is being built and commissioned.
The next big milestone will, in my opinion, be when the company achieves overall positive cashflow and I don't believe that necessarily requires the completion of the CIL plant.
ATB.