RE: My assessment as a believer29 Sep 2024 12:36
Wouldn't say it's not a possibility miner, Q & A should be interesting tomorrow. James Husband said at the Creak presentation that Kor was ramping up at a pace of 2k ounces a month, so that would be 4,800, 6,800, 8,800 or 20k ounces for change on Q3 (60% of defined output) however and I suspect that this update was based on KPI data that didn't account for the mill relining.
Now mill relining is is a tough and dangerous job and takes up to 2-4 weeks to complete at a cost of 5-10% of annual processing availability or in Kor's case 100k tonnes. At the top end of that range it basically wipes out all of September. Therefore I don't think it would be unreasonable to expect Q3 production at Kor to be in the region of 12-