RE: JonathanTidswe1 tweet25 Apr 2019 13:23
Lockedin - they had 4 months to plan this, go to the HSE / OGA for permission and then changed their minds after starting the job which meant they had to then go back and explain why they were doing it....sigh.
The main issue is the isolation of the water zone. Doesn't matter how many holes they make into the casing, if they don't isolate the water you are left with the same problem that they faced in December / January.
So 2 stages of perforations doesn't mean 2 runs.....they are perforating a specific zone multiple times which requires numerous runs , so that means time. They allocated 19 working days for this phase including logging, isolation and what they are currently doing now (perforating).
So safe and steady ....I guess you can call the last 28 months that waiting for Brockham to flow...is just that and the timings they issued (well seeing that the plan has changed...are those timings still relevant or will it take longer than the timings Angus published ...who knows?)