Update on Rare Earth Oxide Separation Progress

5 Feb 2024 07:00

RNS Number : 9441B
Rainbow Rare Earths Limited
05 February 2024
 

 

 

5 February 2024

Rainbow Rare Earths Limited

("Rainbow" or "the Company")

LSE: RBW

 

Update on Rare Earth Oxide Separation Progress

· Group separation of the rare earth elements has been achieved in the initial ion exchange test-work ongoing in USA

· The successful achievement of the group separation paves the way for the delivery of individual separated rare earth oxides. A high purity neodymium and praseodymium (together "NdPr") separated rare earth oxide is the initial focus of the back-end piloting campaign, with the dysprosium ("Dy") and terbium ("Tb") oxides to follow thereafter

· Group separation for the samarium ("Sm"), europium ("Eu") and gadolinium ("Gd") elements holds promise and could provide a complementary revenue stream as a combined oxide

· Rainbow is attending the 121 Mining Investment Conference in Cape Town, South Africa this week. A copy of the 121 conference presentation is available on the Company's website at: https://www.rainbowrareearths.com/investors/results-reports-presentations/

 

News Release

Rainbow Rare Earths is pleased to announce an update on progress with regards to the ongoing rare earth oxide separation work underway at the back-end pilot plant, which is located at the facilities of Rainbow's technical partner K-Technologies, Inc. ("K-Tech") in Florida. 

The back-end plant process utilises continuous ion exchange ("CIX") and continuous ion chromatography ("CIC") to produce separated rare earth oxides. The innovative application of this established technology has been pioneered by K-Tech in the rare earth space and replaces traditional solvent extraction which uses toxic and flammable solvents and diluents and requires more than 100 separate stages.

As previously announced, the optimal feed for the back-end process has been determined by Rainbow and K-Tech as a cerium-depleted mixed rare earth carbonate, which provides a higher-grade feedstock to the back-end separation circuit.

The initial separation at the back-end pilot plant has been achieved using the mixed rare earth carbonate successfully produced from phosphogypsum from the Phalaborwa project. This material, which includes cerium, was previously shipped to K-Tech from the front-end pilot plant located at the Johannesburg facilities of the Council for Mineral Technology ("Mintek"), a global leader in mineral processing, extractive metallurgy, and related fields. Cerium depletion test work is ongoing at both K-Tech and Mintek and the cerium-depleted carbonate, once available, is expected to produce better results in the CIX / CIC separation circuits.

The back-end plant process comprises three main stages, as depicted in the simplified CIX / CIC block flow diagram to follow, being:

1. Stage 1: Impurity Removal via CIX;

2. Stage 2: Group separation via CIC (in two steps); and

3. Stage 3: Individual separation via CIC (in three steps).

Stage 1 removes remaining impurities from the mixed rare earths feed. Stage 2 then uses CIC to separate the targeted rare earth elements (NdPr, Dy, Tb) into groups from the uneconomic rare earth elements. Stage 3 purifies the separated target groups into the individual desired separated rare earth oxides.

 

A summary of the progress made with the back-end flowsheet is as follows:

· successful impurity removal in the initial ion-exchange step providing suitable feed solution for group separation;

· successful separation of the uneconomic lanthanum and cerium group;

· successful group separation in the first step of the chromatography stage, delivering a NdPr group, grading ca. 68%, as feed for purification in the subsequent individual chromatography separation steps;

· considerable upgrading of the concentration of the Dy and Tb from a combined feed grade of 0.9% to 14.6%, which requires separation from the SEG group; and

· good separation of the samarium, europium and gadolinium ("SEG") group at a grade of ca. 63%, which as a group provides the strong potential for an additional valuable product line as a combined Sm-Eu-Gd oxide concentrate.

The current focus of the pilot plant test work at K-Tech is to optimise the second stage of the chromatography process to produce a 99.5% NdPr product. This will be followed by CIC testing to separate and purify the separate Dy and Tb oxides.

In addition, the production of a separated and purified SEG oxide product will be evaluated and followed up. Initial indications are that Phalaborwa could produce ca. 500 tonnes per annum of a saleable SEG product which, in addition to the previously announced off-take for the residual gypsum, provides the potential for an additional revenue stream for the project with minimal capital and operating costs.

George Bennett, CEO of Rainbow, commented: "I am very pleased with the continued progress to date validating our front-end process flow sheet and the K-Tech CIX / CIC process flow sheet for the back-end. The back-end process is on track to deliver separated high purity rare earth oxides of NdPr, Dy and Tb, the four most economically important rare earth elements due to their crucial role in the green energy transition. It is also notable that we have achieved positive separation in the chromatography circuit of the SEG group of rare earth oxides, which could add another very saleable product and revenue stream to Rainbow at minimal cost.''

The four rare earths that will be produced at Phalaborwa - NdPr, Dy and Tb - are all designated as critical minerals further to their important role in the transition to the green economy. As vital components of permanent magnets, these rare earth elements are used within electric vehicles and wind turbines, as well as many other advanced technologies including those required for strategic defence purposes, such as guided missiles, drones, electronic displays, sonar and jet fighter engines. The SEG rare earths are samarium (used in magnets), europium (used in optical displays) and gadolinium (used in medical and nuclear applications).

 

For further information, please contact:

 

Rainbow Rare Earths Ltd

Company

George Bennett

Pete Gardner

+27 82 652 8526

 

 

IR

Cathy Malins

+44 7876 796 629

cathym@rainbowrareearths.com

Berenberg

Broker

Matthew Armitt

Jennifer Lee

 

+44 (0) 20 3207 7800

Stifel

 

Broker

Ashton Clanfield

Varun Talwar

 

+44 20 7710 7600

Tavistock Communications

PR/IR

Charles Vivian

Tara Vivian-Neal

+44 (0) 20 7920 3150

rainbowrareearths@tavistock.co.uk

 

 

Notes to Editors:

About Rainbow:

Rainbow Rare Earths aims to be a forerunner in the establishment of an independent and ethical supply chain of the rare earth elements that are driving the green energy transition. It is doing this successfully via the identification and development of secondary rare earth deposits that can be brought into production quicker and at a lower cost than traditional hard rock mining projects, with a focus on the permanent magnet rare earth elements neodymium and praseodymium, dysprosium and terbium.

The Company is focused on the development of the Phalaborwa Rare Earths Project in South Africa and the earlier stage Uberaba Project in Brazil. Both projects entail the recovery of rare earths from phosphogypsum stacks that occur as the by-product of phosphoric acid production, with the original source rock for both deposits being a hardrock carbonatite. Rainbow intends to use a proprietary separation technique developed by and in conjunction with its partner K-Technologies, Inc., which simplifies the process of producing separated rare earth oxides (versus traditional solvent extraction), leading to cost and environmental benefits.

The Phalaborwa Preliminary Economic Assessment has confirmed strong base line economics for the project, which has a base case NPV10 of US$627 million[1], an average EBITDA operating margin of 75% and a payback period of < two years. Pilot plant operations commenced in 2023, with the project expected to reach commercial production in 2026, just five years after work began on the project by Rainbow.

More information is available at www.rainbowrareearths.com.

 


[1] Net present value using a 10% forward discount rate

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDKZLFBZLLFBBK
Date   Source Headline
5th May 20267:00 amRNSEvaluation of a Listing in the USA
31st Mar 20267:15 amRNSInterim Results for six months to 31 December 2025
31st Mar 20267:00 amRNSSubscription raises £11.1m from investors
17th Mar 20267:00 amRNS-RPublication of New Investor Presentation
17th Mar 20267:00 amRNS-RPublication of New Investor Presentation
11th Mar 20267:00 amRNSMosaic Agreement and Uberaba Economic Assessment
11th Mar 20267:00 amRNSMosaic Agreement and Uberaba Economic Assessment
9th Feb 20267:00 amRNSPilot Plant Producing Commercial Mixed REE Product
14th Jan 20265:35 pmRNSPDMR Shareholding
13th Jan 20267:00 amRNSPilot Plant Commences Operations in Johannesburg
25th Nov 20257:00 amRNSSX Adoption Yields 99.5% Pure Rare Earth Products
24th Nov 20257:00 amRNSYttrium Price Surge Improves Phalaborwa Economics
12th Nov 20259:38 amRNSResults of Annual General Meeting
10th Nov 20257:00 amRNSPhalaborwa Resource Update to include Yttrium
27th Oct 20258:13 amRNSPublication of Annual Report and Notice of AGM
27th Oct 20257:00 amRNSPreliminary Results for Year-end 30 June 2025
22nd Sep 20257:00 amRNSFurther Major Advancement in Phalaborwa Test Work
1st Sep 20257:00 amRNSCIX Test Work shows Very High Purity Separation
4th Jul 20257:00 amRNSIssue of Shares to Directors under Incentive Plan
17th Jun 20257:00 amRNSEconomic Assessment for Uberaba Project in Brazil
3rd Jun 20257:00 amRNSUpdate on Laboratory Test Work in South Africa
29th May 20257:00 amRNS-RCollaboration with Curation Connect
21st May 20257:00 amRNS-RRainbow joins the Rare Earth Industry Association
19th Mar 20257:00 amRNSInterim Results for 6 Months to 31 December 2024
16th Dec 20247:00 amRNSInterim Study confirms Phalaborwa viability
7th Nov 20243:15 pmRNSResult of AGM
6th Nov 20247:00 amRNSDirector/PDMR Shareholding
23rd Oct 20249:00 amRNSPublication of Annual Report and Notice of AGM
18th Oct 20247:00 amRNSPreliminary Results for Year-end 30 June 2024
25th Sep 20247:00 amRNSCompletion of Ecora Royalty Transaction
18th Sep 20247:00 amRNSPhalaborwa Update
11th Sep 20247:00 amRNSUpdated Mineral Resource Estimate for Phalaborwa
3rd Sep 20247:00 amRNSGrant of Share Based Remuneration
1st Jul 20247:00 amRNSRoyalty Agreement with Ecora & US$10m raise
19th Jun 20247:00 amRNSPilot Plant Update
18th Apr 20243:50 pmRNSDirector/PDMR Shareholding
16th Apr 20247:00 amRNSPositive Initial Leaching and Mineralogy Results
28th Mar 20247:00 amRNSInterim Results
20th Mar 202411:37 amRNSPublication of Conference Presentation
26th Feb 20247:00 amRNSResource Update
5th Feb 20247:00 amRNSUpdate on Rare Earth Oxide Separation Progress
31st Jan 20247:00 amRNSPublication of Site Visit Presentation
18th Jan 20247:24 amRNSUS Congressional Delegation hosted at Phalaborwa
16th Jan 20247:00 amRNSAppointment of Stifel as Joint Broker
11th Jan 20247:00 amRNSRare Earth Oxide separation commences in the U.S.
6th Dec 20237:00 amRNSConditional shares issue & share options exercise
5th Dec 20237:00 amRNSDFC to fund proposed $50M TechMet investment
1st Dec 20237:00 amRNSRBW's partner K-Tech presents at Congress hearing
21st Nov 20237:00 amRNSResults of Annual General Meeting
8th Nov 20237:00 amRNSTechMet option to invest US$50m in Phalaborwa

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.