Pin to quick picksRainbow Rare Earths Regulatory News (RBW)

Share Price Information for Rainbow Rare Earths (RBW)

Share Price is delayed by 15 minutes
Get Live Data
21.75    -0.50 (-2.25%)
Bid:
21.00
Ask:
22.50
Spread: 1.50 (7.143%)
Market Cap: £152.18m
RBW Live PriceLast checked at - London Stock Exchange

Intraday Rainbow Rare Earths Share Chart

Updated Mineral Resource Estimate for Phalaborwa

11 Sep 2024 07:00

RNS Number : 6490D
Rainbow Rare Earths Limited
11 September 2024
 

11 September 2024

 

Rainbow Rare Earths Limited

("Rainbow" or "the Company")

LSE: RBW

 

Updated JORC-compliant Mineral Resource Estimate ("MRE") for Phalaborwa

 

· Updated MRE confirms a 15% increase in the overall size of the Phalaborwa Resource, adding an additional two years to the project life.

· Total Measured, Indicated and Inferred Resource of 35.0 Mt at 0.44% TREO, with a near doubling in the material now classified as Measured.

· The light rare earth elements ("REEs") neodymium ("Nd") and praseodymium ("Pd") represent 29% and the heavy REEs dysprosium ("Dy") and terbium ("Tb") represent 1% and 0.3% respectively - all four of these REEs are considered critical minerals essential to the green energy transition.

· The MRE now reports the full range of recoverable REEs that may have economic value for Rainbow in the future, being the SEG group (samarium, europium and gadolinium), lanthanum ("La") and cerium ("Ce").

· At spot pricing, including Nd/Pr at ca. US$62.5/kg[1], the MRE has an in-situ metal oxide value of ca. US$3.7 billion REEs, with considerable upside based on the forecast strong demand outlook for permanent magnet REEs.

 

NEWS RELEASE

Further to the Resource Update released on 26 February 2024, today's announcement reflects the publication of a new MRE for Phalaborwa prepared in accordance with the guidelines of the JORC Code (2012 Edition) ("JORC"). The full MRE can be accessed at https://www.rainbowrareearths.com/project/phalaborwa/.

As indicated in the February announcement, the application of updated bulk density estimates and additional drilling for the Phalaborwa phosphogypsum stacks has led to an increase in the Resource by 15% from 30.4 Mt to 35.0 Mt, reported at a 0.2% TREO cut-off grade. At projected production rates, this has extended the project life from 14 years to 16 years.

George Bennett, CEO of Rainbow, commented: "The publication of an updated JORC-compliant Resource for Phalaborwa reaffirms the huge value intrinsic to this project, which contains economic quantities of all four of the critical magnet REEs. It also points to the potential for value from other recoverable REEs, which are currently not included in our project economics, and the MRE has an in-situ metal oxide value of ca. US$3.7 billion even at today's lower spot prices. It's worth noting that this is a very different type of Resource to that of a hard rock mining project, sitting at surface with a relatively homogenous distribution in the phosphogypsum stacks. Therefore, we intend to process the entirety of the stacks, allowing us to generate value from the full 35 Mt Resource."

The four most economically important REEs, being Nd, Pr, Dy and Tb, together represent over 30% of the basket by volume at Phalaborwa and 96% by value. These REEs have been designated globally as critical minerals for the green energy transition due to their use in the permanent magnets essential for electric vehicles and wind turbines. Furthermore, they are considered to be among those critical minerals most at risk in terms of supply chain vulnerabilities.

For the first time, the MRE now includes the full range of recoverable REEs that may have economic value for Rainbow in the future, being the SEG group, La and Ce. At spot prices, the MRE including these ancillary REEs has an in-situ metal oxide value of ca. US$3.7 billion. We have also confirmed that the process residue gypsum is a saleable product, allowing Rainbow to realise further value from the Resource.

The updated MRE confirms very low levels of radioactive elements, further attesting to the 'green' credentials of this project, which will recover REEs from a waste product and rehabilitate an industrial site over time. Uranium is estimated at 1.8 ppm and thorium is estimated at 48ppm, at which levels they can be considered trace elements.

Measured, Indicated and Inferred Mineral Resource Estimate

The MRE is located in two adjacent historically processed phosphogypsum stacks (termed Stack A and Stack B) on the Phalaborwa project site. The MRE update was completed in July 2024 and is based on additional drilling and sampling completed during 2023. Samples were initially sent to Ardaman and Associates, Inc., a Tetra Tech Company ("Ardaman"), in the USA for bulk density calculations before being shipped back to SGS in South Africa for grade assays.

Notes:

1. TREO = Total Rare Earth Oxide; ppm = parts per million

2. Resource figures are reported gross; Rainbow owns an 85% interest in the Phalaborwa project, with an option to increase ownership to 100%

3. The Mineral Resource is reported at a nominal 0.2% TREO cut-off grade

4. No constraining shell is required as stacks are above ground level and no selective reclamation is required

5. Mineral resources are not mineral reserves and do not have demonstrated economic viability

6. The 'Total' rows do not always tally due to rounding

7. The full Resource tables are set out in the Appendix

 

The MRE is classified as Measured, Indicated and Inferred Mineral Resources of 46%, 43% and 11% deposit tonnage respectively (July 2023 Resource: Measured, Indicated and Inferred Mineral Resources of 24%, 53% and 23% deposit tonnage respectively), representing increased confidence as a result of recent infill drilling.

The MRE is noted as being relatively homogenous in nature, with no selective reclamation of the stacks required as 99.7% of the phosphogypsum tonnage is above the 0.2% TREO cut-off. Due to the nature of the Resource sitting at surface and the associated water limiting drill accessibility, Rainbow is not planning to do further infill drilling and the Inferred portion will be included in the project's forthcoming Definitive Feasibility Study. It is anticipated that the full Resource will be processed as part of the project life.

Competent Persons Statement

The information in this report that relates to the Mineral Resources for the Phalaborwa project is based on, and fairly represents, information compiled or reviewed by Mr Malcolm Titley, a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy and the Australian Institute of Geoscientists. Mr Titley is employed by Maja Mining Limited, an independent consulting company.

Mr Titley has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr Titley consents to the inclusion of information from this report in Rainbow public releases using his information in the form and context in which it appears.

For further information, please contact:

 

Rainbow Rare Earths Ltd

Company

George Bennett

Pete Gardner

+27 82 652 8526

 

 

IR

Cathy Malins

+44 7876 796 629

cathym@rainbowrareearths.com

Berenberg

Broker

Matthew Armitt

Jennifer Lee

 

+44 (0) 20 3207 7800

Stifel

 

Broker

Ashton Clanfield

Varun Talwar

 

+44 20 7710 7600

Tavistock Communications

PR/IR

Charles Vivian

Tara Vivian-Neal

+44 (0) 20 7920 3150

rainbowrareearths@tavistock.co.uk

 

Notes to Editors:

About Rainbow:

Rainbow Rare Earths aims to be a forerunner in the establishment of an independent and ethical supply chain of the rare earth elements that are driving the green energy transition. It is doing this successfully via the identification and development of secondary rare earth deposits that can be brought into production quicker and at a lower cost than traditional hard rock mining projects, with a focus on the permanent magnet rare earth elements neodymium and praseodymium, dysprosium and terbium.

The Company is focused on the development of the Phalaborwa Rare Earths Project in South Africa and the earlier stage Uberaba Project in Brazil. Both projects entail the recovery of rare earths from phosphogypsum that occurs as the by-product of phosphoric acid production, with the original source rock for both deposits being a hardrock carbonatite.

The Phalaborwa Preliminary Economic Assessment has confirmed strong base line economics for the project, which has a base case NPV10 of US$627 million, an average EBITDA operating margin of 75% and a payback period of < two years.

More information is available at www.rainbowrareearths.com.

Appendix

MRE - REE Proportions

JORC 2012

Stack

Mt

TREO %

Nd

Pr

NdPr

Dy

Tb

Eu

Sm

Gd

La

Ce

LREO

HREO

SEGO

Ga

F

Th

U

Dry BD

Moisture

Measured

Stack A

10.8

0.4

23.6

5.7

29.3

1.0

0.3

0.8

4.0

3.0

17.4

41.6

92.2

5.5

7.8

10

0.8

48.6

1.7

1.37

25

Stack B

5.2

0.5

23.3

5.9

29.1

0.9

0.3

0.8

3.9

2.9

17.4

42.2

92.5

5.4

7.6

9

0.7

45.0

2.1

1.33

27

Total

16.0

0.5

23.5

5.7

29.2

1.0

0.3

0.8

4.0

3.0

17.4

41.8

92.3

5.4

7.7

10

0.7

47.4

1.8

1.36

26

Indicated

Stack A

11.0

0.4

23.3

5.5

28.8

1.0

0.3

0.8

3.9

2.9

17.2

42.2

92.2

5.4

7.6

11

0.6

47.7

1.8

1.46

22

Stack B

3.9

0.5

23.2

5.7

28.8

1.0

0.3

0.8

3.9

2.8

17.6

42.4

92.7

5.2

7.5

10

0.7

42.9

2.0

1.31

27

Rubble/

Mixed

0.4

0.3

25.3

5.4

30.7

1.0

0.3

0.8

4.5

2.8

16.4

40.5

92.2

5.3

8.1

6

1.3

28.5

1.9

1.42

27

Total

15.2

0.4

23.3

5.6

28.9

1.0

0.3

0.8

3.9

2.9

17.3

42.2

92.3

5.4

7.6

11

0.7

46.0

1.9

1.42

24

Inferred

Stack A

1.7

0.4

23.4

5.5

28.9

1.0

0.3

0.8

3.9

2.8

17.0

42.5

92.3

5.3

7.5

9

0.6

46.0

2.1

1.48

21

Stack B

1.6

0.4

23.2

5.5

28.7

1.0

0.3

0.8

4.0

2.8

17.7

42.1

92.5

5.3

7.7

11

0.7

40.2

2.0

1.33

27

Rubble/

Mixed

0.6

0.3

24.3

5.8

30.1

0.9

0.3

0.8

4.6

2.7

17.3

40.5

92.5

5.2

8.2

5

1.1

31.1

1.5

1.42

25

Total

3.8

0.4

23.4

5.6

29.0

1.0

0.3

0.8

4.0

2.8

17.3

42.1

92.4

5.3

7.7

9

0.7

41.4

2.0

1.40

24

Grand Total

 

35.0

0.4

23.4

5.6

29.0

1.0

0.3

0.8

4.0

2.9

17.3

42.0

92.3

5.4

7.7

10

0.7

46.1

1.8

1.39

25

 

Notes

1. TREO = Total Rare Earth Oxide, HREO = Heavy Rare Earth Oxide, LREO = Light Rare Earth Oxide, SEGO = SEG Oxide

2. The Mineral Resource is reported at a 0.2% TREO cut-off grade

3. The individual REEs set out in the table refer to the following oxides, set out as % proportions of TREO; Nd2O3, Pr6O11, Dy2O3, Tb4O7, Eu2O3, Sm2O3, Gd2O3, La2O3, Ce2O3, Ce2O3

4. NdPr, LREO, HREO and SEGO are set out as % proportions of TREO

5. Ga, Th, U are shown as parts per million (ppm), F is shown as %

6. Moisture content is set out as %

7. No constraining shell is required as stacks are above ground level

8. Adequate initial metallurgical testwork and financial analysis has been completed to satisfy reasonable prospects for economic evaluation

9. The favoured mineral processing route uses a continuous ion exchange (to remove impurities) followed by REE leach and REE refining to produce three saleable products: neodymium/praseodymium oxide, dysprosium oxide, and terbium oxide; all processing is expected to be on-site at the Phalaborwa Mining Complex adjacent to the phosphogypsum stacks

10. Tonnages are rounded to the nearest 100,000 tonnes to reflect this as an estimate

 

MRE - REE Grades

JORC 2012

Stack

Mt

TREO

%

LREO

%

HREO

%

SEGO

%

F

%

Th

ppm

U

ppm

Nd2O3

%

Pr6O11

%

Dy2O3

%

Tb4O7

%

Sm2O3

%

Eu2O3

%

Gd2O3

%

La2O3

%

Ce2O3

%

Dry BD

Moisture

Measured

Stack A

10.8

0.44

0.41

0.02

0.03

0.8

49

1.7

0.104

0.025

0.004

0.001

0.018

0.004

0.013

0.077

0.184

1.37

25

Stack B

5.2

0.47

0.43

0.02

0.04

0.7

45

2.1

0.109

0.028

0.004

0.002

0.018

0.004

0.014

0.081

0.198

1.33

27

Total

16.0

0.45

0.42

0.02

0.03

0.7

47

1.8

0.106

0.026

0.004

0.001

0.018

0.004

0.013

0.078

0.188

1.36

26

Indicated

Stack A

11.0

0.42

0.39

0.02

0.03

0.6

48

1.8

0.098

0.023

0.004

0.001

0.016

0.003

0.012

0.072

0.177

1.46

22

Stack B

3.9

0.46

0.42

0.02

0.03

0.7

43

2.0

0.106

0.026

0.004

0.001

0.018

0.004

0.013

0.080

0.193

1.31

27

Rubble/

Mixed

0.4

0.30

0.28

0.02

0.02

1.3

29

1.9

0.075

0.016

0.003

0.001

0.013

0.002

0.008

0.050

0.123

1.42

27

Total

15.2

0.43

0.39

0.02

0.03

0.7

46

1.9

0.099

0.024

0.004

0.001

0.017

0.003

0.012

0.074

0.180

1.42

24

Inferred

Stack A

1.7

0.41

0.38

0.02

0.03

0.6

46

2.1

0.097

0.023

0.004

0.001

0.016

0.003

0.012

0.071

0.176

1.48

21

Stack B

1.6

0.44

0.41

0.02

0.03

0.7

40

2.0

0.103

0.025

0.004

0.001

0.018

0.004

0.013

0.079

0.188

1.33

27

Rubble/

Mixed

0.6

0.31

0.28

0.02

0.02

1.1

31

1.5

0.074

0.018

0.003

0.001

0.014

0.003

0.008

0.053

0.125

1.42

25

Total

3.8

0.41

0.38

0.02

0.03

0.7

41

2.0

0.096

0.023

0.004

0.001

0.016

0.003

0.012

0.071

0.173

1.40

24

Grand Total

 

35.0

0.44

0.40

0.02

0.03

0.7

46.0

1.8

0.102

0.025

0.004

0.001

0.017

0.003

0.013

0.075

0.183

1.39

25

 

Notes

1. TREO = Total Rare Earth Oxide, HREO = Heavy Rare Earth Oxide, LREO = Light Rare Earth Oxide, SEGO = SEG Oxide

2. The Mineral Resource is reported at a 0.2% TREO cut-off grade

3. Moisture content is set out as %

4. No constraining shell is required as stacks are above ground level

5. Adequate initial metallurgical testwork and financial analysis has been completed to satisfy reasonable prospects for economic evaluation

6. The favoured mineral processing route uses a continuous ion exchange (to remove impurities) followed by REE leach and REE refining to produce three saleable products: neodymium/praseodymium oxide, dysprosium oxide, and terbium oxide; all processing is expected to be on-site at the Phalaborwa Mining Complex adjacent to the phosphogypsum stacks

7. Tonnages are rounded to the nearest 100,000 tonnes to reflect this as an estimate

 

 

MRE - Contained Metal

Contained Metal (tonnes)

 

JORC 2012

Stack

Mt

Nd2O3

Pr6O11

Dy2O3

Tb4O7

Sm2O3

Eu2O3

Gd2O3

La2O3

Ce2O3

Dry BD

Moisture

Measured

Stack A

10.8

11,214

2,704

466

152

1,896

379

14

8,272

19,831

1.37

25

Stack B

5.2

5,721

1,439

228

79

953

198

7

4,261

10,345

1.33

27

Total

16.0

16,935

4,143

695

230

2,849

577

21

12,533

30,176

1.36

26

Indicated

Stack A

11.0

10,724

2,545

455

145

1,797

371

13

7,929

19,436

1.46

22

Stack B

3.9

4,109

1,009

168

54

693

142

5

3,115

7,515

1.31

27

Rubble/Mixed

0.4

275

60

11

4

50

9

0

183

453

1.42

27

Total

15.2

15,109

3,615

634

202

2,540

521

19

11,227

27,404

1.42

24

Inferred

Stack A

1.7

1,602

379

66

20

264

55

2

1,169

2,920

1.48

21

Stack B

1.6

1,624

388

68

22

280

58

2

1,241

2,953

1.33

27

Rubble/Mixed

0.6

420

100

16

6

80

15

0

299

708

1.42

25

Total

3.8

3,646

867

151

48

624

127

4

2,710

6,580

1.40

24

Grand Total

 

35.0

35,689

8,624

1,479

480

6,012

1,225

44

26,469

64,161

1.39

25

 

Notes

1. The Mineral Resource is reported at a 0.2% TREO cut-off grade

2. Metal Content is quoted to the nearest ton

3. Moisture content is set out as %

4. No constraining shell is required as stacks are above ground level

5. Adequate initial metallurgical testwork and financial analysis has been completed to satisfy reasonable prospects for economic evaluation

6. The favoured mineral processing route uses a continuous ion exchange (to remove impurities) followed by REE leach and REE refining to produce three saleable products: neodymium/praseodymium oxide, dysprosium oxide, and terbium oxide; all processing is expected to be on-site at the Phalaborwa Mining Complex adjacent to the phosphogypsum stacks

7. Tonnages are rounded to the nearest 100,000 tonnes to reflect this as an estimate

 


[1] As at 6 September 2024

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDGPUWWBUPCGQU
Date   Source Headline
5th May 20267:00 amRNSEvaluation of a Listing in the USA
31st Mar 20267:15 amRNSInterim Results for six months to 31 December 2025
31st Mar 20267:00 amRNSSubscription raises £11.1m from investors
17th Mar 20267:00 amRNS-RPublication of New Investor Presentation
17th Mar 20267:00 amRNS-RPublication of New Investor Presentation
11th Mar 20267:00 amRNSMosaic Agreement and Uberaba Economic Assessment
11th Mar 20267:00 amRNSMosaic Agreement and Uberaba Economic Assessment
9th Feb 20267:00 amRNSPilot Plant Producing Commercial Mixed REE Product
14th Jan 20265:35 pmRNSPDMR Shareholding
13th Jan 20267:00 amRNSPilot Plant Commences Operations in Johannesburg
25th Nov 20257:00 amRNSSX Adoption Yields 99.5% Pure Rare Earth Products
24th Nov 20257:00 amRNSYttrium Price Surge Improves Phalaborwa Economics
12th Nov 20259:38 amRNSResults of Annual General Meeting
10th Nov 20257:00 amRNSPhalaborwa Resource Update to include Yttrium
27th Oct 20258:13 amRNSPublication of Annual Report and Notice of AGM
27th Oct 20257:00 amRNSPreliminary Results for Year-end 30 June 2025
22nd Sep 20257:00 amRNSFurther Major Advancement in Phalaborwa Test Work
1st Sep 20257:00 amRNSCIX Test Work shows Very High Purity Separation
4th Jul 20257:00 amRNSIssue of Shares to Directors under Incentive Plan
17th Jun 20257:00 amRNSEconomic Assessment for Uberaba Project in Brazil
3rd Jun 20257:00 amRNSUpdate on Laboratory Test Work in South Africa
29th May 20257:00 amRNS-RCollaboration with Curation Connect
21st May 20257:00 amRNS-RRainbow joins the Rare Earth Industry Association
19th Mar 20257:00 amRNSInterim Results for 6 Months to 31 December 2024
16th Dec 20247:00 amRNSInterim Study confirms Phalaborwa viability
7th Nov 20243:15 pmRNSResult of AGM
6th Nov 20247:00 amRNSDirector/PDMR Shareholding
23rd Oct 20249:00 amRNSPublication of Annual Report and Notice of AGM
18th Oct 20247:00 amRNSPreliminary Results for Year-end 30 June 2024
25th Sep 20247:00 amRNSCompletion of Ecora Royalty Transaction
18th Sep 20247:00 amRNSPhalaborwa Update
11th Sep 20247:00 amRNSUpdated Mineral Resource Estimate for Phalaborwa
3rd Sep 20247:00 amRNSGrant of Share Based Remuneration
1st Jul 20247:00 amRNSRoyalty Agreement with Ecora & US$10m raise
19th Jun 20247:00 amRNSPilot Plant Update
18th Apr 20243:50 pmRNSDirector/PDMR Shareholding
16th Apr 20247:00 amRNSPositive Initial Leaching and Mineralogy Results
28th Mar 20247:00 amRNSInterim Results
20th Mar 202411:37 amRNSPublication of Conference Presentation
26th Feb 20247:00 amRNSResource Update
5th Feb 20247:00 amRNSUpdate on Rare Earth Oxide Separation Progress
31st Jan 20247:00 amRNSPublication of Site Visit Presentation
18th Jan 20247:24 amRNSUS Congressional Delegation hosted at Phalaborwa
16th Jan 20247:00 amRNSAppointment of Stifel as Joint Broker
11th Jan 20247:00 amRNSRare Earth Oxide separation commences in the U.S.
6th Dec 20237:00 amRNSConditional shares issue & share options exercise
5th Dec 20237:00 amRNSDFC to fund proposed $50M TechMet investment
1st Dec 20237:00 amRNSRBW's partner K-Tech presents at Congress hearing
21st Nov 20237:00 amRNSResults of Annual General Meeting
8th Nov 20237:00 amRNSTechMet option to invest US$50m in Phalaborwa

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.