Ben Richardson, CEO at SulNOx, confident they can cost-effectively decarbonise commercial shipping. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksJubilee Metals Regulatory News (JLP)

Share Price Information for Jubilee Metals (JLP)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 6.90
Bid: 6.80
Ask: 7.00
Change: 0.00 (0.00%)
Spread: 0.20 (2.941%)
Open: 6.90
High: 6.90
Low: 6.90
Prev. Close: 6.90
JLP Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

DCM Operations update and Exercise of warrants

6 Mar 2017 09:45

RNS Number : 6017Y
Jubilee Platinum PLC
06 March 2017
 

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

6 March 2017

 

Jubilee Platinum PLC

("Jubilee" or "Company")

 

DCM Operations update

Exercise of warrants

 

Mine-to-Metals specialist Jubilee Platinum plc (AIM: JLP, AltX: JBL) is pleased to provide, on behalf of its subsidiary, Jubilee Tailings Treatment Company Pty Ltd ("JTTC"), a quarterly performance, operational and financial update of its chrome recovery section of the Dilokong Chrome mine tailings project ("DCM Tailings" or "DCM Project") for Q4 2016 as well as a project update for the platinum processing project at Hernic Ferrochrome Pty Ltd ("Hernic").

 

Highlights

DCM Project Q4 2016

· Construction of the new tailings, post chromite removal, storage facility commenced and the first phase of the expansion has been successfully commissioned on 25 January 2017. These tailings contain the enriched platinum material.

· The DCM Project continued production of chromite concentrate at a reduced rate during the construction period. The production rate has been restored to previous levels during February 2017.

· Chromite concentrate production during Q4 was lowered to 19 108 tons for Q4 2016 compared with 28 559 tons for Q3 2016.

· Chromite project earnings increased on the back of a significantly higher chromite price to GBP 1, 837 million (ZAR 31, 792 million) for Q4 2016 compared to Q3 2016.

· Earnings attributable to Jubilee for Q4 2016 from chromite concentrate production reduced due to the lower concentrate production and loss of incentives to GBP 0,465 million (ZAR 8, 033 million,) compared with Q3 2016.

· The first 3rd party chrome and platinum containing material is scheduled to be processed at DCM during Q1 2017.

 

Leon Coetzer, Chief Executive commented:

"The operating results are satisfactory against the constraints of the expansion of the tailings storage facility. The DCM Project performed to maintain production output during this challenging construction period. The expansion of the tailings facility was completed on time allowing the project to restore its operational throughput.

The commissioning and ramp-up of the Hernic chromite and platinum recovery plant remains a key focus. We will provide an update on the Hernic project shortly as we start delivering product from the operation.

The significant milestone reached with the Tjate platinum project continues to demonstrate our aggressive pursuit to continuously advance the Company's mission of a Mines to Metals Company while growing shareholder value. As stated before we are confident that we will shortly conclude a further acquisition with discussions progressing favourably in other areas of acquisition and joint venture."

Chromite concentrate tons produced

Project revenue (GBP'000)

Project revenue (ZAR'000)

Project earnings (GBP'000)

Project earnings (ZAR'000)

Jubilee attributable project earnings (GBP'000)

Jubilee attributable project earnings (ZAR'000)

Q2 2016

(May, June 2016)

15 188

1,002

19,137

744

14,203

456

8,710

Q3 2016

(July, August, September 2016)

28 559

2 086

37 360

1 548

27 702

888

15 887

Q4 2016

(October, November, December 2016)

19 108

2 754

47 662

1 837

31 792

465

8 033

% change Q3 on Q4

(33.09%)

32.01%

27.57%

18.68%

14.77%

(47.60%)

(49.43%)

YTD since start of project in May 2016

62 855

5 842

104 159

4 128

73 697

1 809

32 630

 

 

DCM OPERATIONAL AND FINANCIAL PERFORMANCE

 

 

As announced previously, further increases in operational throughput requires the expansion of the new tailings (post chromite removal) storage facility. The expansion of the facility has commenced and the first phase of the expansion project completed on 25 January 2017 allowing the production rates to be restored to previous levels. The DCM Project team managed to continue production throughout the construction phase at a reduced production rate. Production rates have been restored during February 2017 on the back of the successful first phase tailings storage expansion. The further expansion phases of the project will not directly impact the production rates at the DCM Project.

All chromite production to date at DCM continues to be from the processing of surface tailings alone. The first 3rd party chrome and platinum containing material is scheduled to be processed at DCM during Q1 2017. Stated Project earnings are net of operational cost and cost of chromite concentrate sales.

Jubilee also announces that it has received notification to exercise 10 000 000 warrants at a price of 4.725p (ZAR75.65c) per warrant share. This exercise leaves 8 244 825 outstanding warrants priced at 4.725p. The exercise of the warrant shares amounts, in aggregate, to a cash value of £472,500 (ZAR 7,564,725).

The warrant shares are expected to be admitted to trading on AIM and listed on the AltX of the JSE Limited on or about 10 March 2017 and will rank pari passu with the ordinary shares of the Company in issue.

The Company's total issued share capital, after the issue of the warrant shares, will be 1 052 360 942 ordinary shares. As the Company does not hold any shares in Treasury, this figure may be used by shareholders in the Company as the denominator for the calculations by which they will determine if they are required to notify their interest in, or a change to their interest in, the share capital of the Company following Admission.

 

Contacts

Jubilee Platinum plc

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913Andrew SarosiTel +44 (0)1752 221937

JSE Sponsor

Sasfin Capital, a division of Sasfin Bank LimitedSharon OwensTel +27 (0)11 809 7500

Nominated Adviser

SPARK Advisory Partners LimitedSean Wyndham-Quin/Mark BradyTel: +44 (0)203 368 3555

Broker

Beaufort Securities LimitedJon BellissTel: +44 (0) 20 7382 8300

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGCGDXGSGBGRL
Date   Source Headline
14th Nov 20197:36 amRNSResults for year ended 30 June 2019 & AGM Notice
5th Nov 20198:30 amRNSAcquisition of all chrome rights at Hernic
24th Oct 20193:11 pmRNSAcquisition at Hernic: Transforming Operations
24th Sep 20197:00 amRNSNew Corporate Presentation
17th Sep 20197:00 amRNSKabwe Multi-Metal Processing Project Update
5th Sep 20198:00 amRNSWindsor PGM Project - Full Operational Status
23rd Aug 201910:15 amRNSCompletion of Acquisition in Kabwe & Joint Broker
5th Aug 20199:00 amRNSSix Monthly Operations Update
11th Jul 20197:00 amRNSProjects Update
5th Jun 20191:45 pmRNSProjects Update
9th May 20197:00 amRNSQuarterly Operations Update Q1 2019
3rd May 201912:30 pmRNSTR-1: notification of major holdings
23rd Apr 20197:00 amRNSPrice Monitoring Extension
5th Apr 20192:05 pmRNSSecond Price Monitoring Extn
5th Apr 20192:00 pmRNSPrice Monitoring Extension
4th Apr 20194:41 pmRNSTR-1: notification of major holdings
3rd Apr 20192:26 pmRNSTR-1 NOTIFICATION OF CHANGE IN MAJOR HOLDINGS
2nd Apr 20194:40 pmRNSSecond Price Monitoring Extn
2nd Apr 20194:35 pmRNSPrice Monitoring Extension
29th Mar 20191:35 pmRNSVoting Rights and Capital
29th Mar 201910:38 amRNSTR-1: Form for notification of major holdings
28th Mar 20197:00 amRNSUnaudited interim results
21st Mar 201910:58 amRNSFunding secured for Kabwe Project and Acquisition
20th Mar 20194:18 pmRNSGeneral Operations and Projects Update
17th Jan 20198:30 amRNSQuarterly Operations Update Q4 2018
18th Dec 201812:38 pmRNSTR-1: Notification of major holdings
18th Dec 20188:30 amRNSTR-1: notification of major holdings
17th Dec 20187:00 amRNSCommissioning of fine chrome operation commences
10th Dec 20187:15 amRNSJubilee acquires major Chrome Processing Operation
6th Dec 20181:00 pmRNSResults of AGM
4th Dec 20187:02 amRNSSecond Price Monitoring Extn
4th Dec 20187:01 amRNSPrice Monitoring Extension
3rd Dec 20184:40 pmRNSSecond Price Monitoring Extn
3rd Dec 20184:35 pmRNSPrice Monitoring Extension
28th Nov 20181:30 pmRNSJubilee Live Interactive Webcast
14th Nov 20182:40 pmRNSAudited results for the year ended 30 June 2018
5th Nov 20188:00 amRNSMarket Update
17th Oct 20189:30 amRNSQuarterly Operations Update Q3 2018
3rd Aug 20187:00 amRNSClarification on BMR Group PLC & the Kabwe Project
19th Jul 20187:00 amRNSQuarterly Operations Update Q2 2018
2nd Jul 20187:00 amRNSKabwe Project Status Update
21st Jun 20183:00 pmRNSBoard Changes
12th Jun 20182:02 pmRNSTR-1: notification of major holdings
11th Jun 20188:30 amRNSPlacement of BMR Shares fully executed
7th Jun 20187:00 amRNSProjects Status Update
4th Jun 20189:15 amRNSKabwe and BMR Group PLC ("BMR") Update
2nd May 20187:00 amRNSJubilee Executes Kabwe Project Agreements
18th Apr 20187:00 amRNSJubilee Executes Processing Agreement
17th Apr 20187:00 amRNSQuarterly Operations Update & Tjate Share Issue
5th Apr 20187:00 amRNSKabwe Mining Licence Reinstated

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.