We would love to hear your thoughts about our site and services, please take our survey here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksJubilee Metals Regulatory News (JLP)

Share Price Information for Jubilee Metals (JLP)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 6.90
Bid: 6.80
Ask: 7.00
Change: 0.00 (0.00%)
Spread: 0.20 (2.941%)
Open: 6.90
High: 6.90
Low: 6.90
Prev. Close: 6.90
JLP Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

DCM Operations update and Exercise of warrants

6 Mar 2017 09:45

RNS Number : 6017Y
Jubilee Platinum PLC
06 March 2017
 

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

6 March 2017

 

Jubilee Platinum PLC

("Jubilee" or "Company")

 

DCM Operations update

Exercise of warrants

 

Mine-to-Metals specialist Jubilee Platinum plc (AIM: JLP, AltX: JBL) is pleased to provide, on behalf of its subsidiary, Jubilee Tailings Treatment Company Pty Ltd ("JTTC"), a quarterly performance, operational and financial update of its chrome recovery section of the Dilokong Chrome mine tailings project ("DCM Tailings" or "DCM Project") for Q4 2016 as well as a project update for the platinum processing project at Hernic Ferrochrome Pty Ltd ("Hernic").

 

Highlights

DCM Project Q4 2016

· Construction of the new tailings, post chromite removal, storage facility commenced and the first phase of the expansion has been successfully commissioned on 25 January 2017. These tailings contain the enriched platinum material.

· The DCM Project continued production of chromite concentrate at a reduced rate during the construction period. The production rate has been restored to previous levels during February 2017.

· Chromite concentrate production during Q4 was lowered to 19 108 tons for Q4 2016 compared with 28 559 tons for Q3 2016.

· Chromite project earnings increased on the back of a significantly higher chromite price to GBP 1, 837 million (ZAR 31, 792 million) for Q4 2016 compared to Q3 2016.

· Earnings attributable to Jubilee for Q4 2016 from chromite concentrate production reduced due to the lower concentrate production and loss of incentives to GBP 0,465 million (ZAR 8, 033 million,) compared with Q3 2016.

· The first 3rd party chrome and platinum containing material is scheduled to be processed at DCM during Q1 2017.

 

Leon Coetzer, Chief Executive commented:

"The operating results are satisfactory against the constraints of the expansion of the tailings storage facility. The DCM Project performed to maintain production output during this challenging construction period. The expansion of the tailings facility was completed on time allowing the project to restore its operational throughput.

The commissioning and ramp-up of the Hernic chromite and platinum recovery plant remains a key focus. We will provide an update on the Hernic project shortly as we start delivering product from the operation.

The significant milestone reached with the Tjate platinum project continues to demonstrate our aggressive pursuit to continuously advance the Company's mission of a Mines to Metals Company while growing shareholder value. As stated before we are confident that we will shortly conclude a further acquisition with discussions progressing favourably in other areas of acquisition and joint venture."

Chromite concentrate tons produced

Project revenue (GBP'000)

Project revenue (ZAR'000)

Project earnings (GBP'000)

Project earnings (ZAR'000)

Jubilee attributable project earnings (GBP'000)

Jubilee attributable project earnings (ZAR'000)

Q2 2016

(May, June 2016)

15 188

1,002

19,137

744

14,203

456

8,710

Q3 2016

(July, August, September 2016)

28 559

2 086

37 360

1 548

27 702

888

15 887

Q4 2016

(October, November, December 2016)

19 108

2 754

47 662

1 837

31 792

465

8 033

% change Q3 on Q4

(33.09%)

32.01%

27.57%

18.68%

14.77%

(47.60%)

(49.43%)

YTD since start of project in May 2016

62 855

5 842

104 159

4 128

73 697

1 809

32 630

 

 

DCM OPERATIONAL AND FINANCIAL PERFORMANCE

 

 

As announced previously, further increases in operational throughput requires the expansion of the new tailings (post chromite removal) storage facility. The expansion of the facility has commenced and the first phase of the expansion project completed on 25 January 2017 allowing the production rates to be restored to previous levels. The DCM Project team managed to continue production throughout the construction phase at a reduced production rate. Production rates have been restored during February 2017 on the back of the successful first phase tailings storage expansion. The further expansion phases of the project will not directly impact the production rates at the DCM Project.

All chromite production to date at DCM continues to be from the processing of surface tailings alone. The first 3rd party chrome and platinum containing material is scheduled to be processed at DCM during Q1 2017. Stated Project earnings are net of operational cost and cost of chromite concentrate sales.

Jubilee also announces that it has received notification to exercise 10 000 000 warrants at a price of 4.725p (ZAR75.65c) per warrant share. This exercise leaves 8 244 825 outstanding warrants priced at 4.725p. The exercise of the warrant shares amounts, in aggregate, to a cash value of £472,500 (ZAR 7,564,725).

The warrant shares are expected to be admitted to trading on AIM and listed on the AltX of the JSE Limited on or about 10 March 2017 and will rank pari passu with the ordinary shares of the Company in issue.

The Company's total issued share capital, after the issue of the warrant shares, will be 1 052 360 942 ordinary shares. As the Company does not hold any shares in Treasury, this figure may be used by shareholders in the Company as the denominator for the calculations by which they will determine if they are required to notify their interest in, or a change to their interest in, the share capital of the Company following Admission.

 

Contacts

Jubilee Platinum plc

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913Andrew SarosiTel +44 (0)1752 221937

JSE Sponsor

Sasfin Capital, a division of Sasfin Bank LimitedSharon OwensTel +27 (0)11 809 7500

Nominated Adviser

SPARK Advisory Partners LimitedSean Wyndham-Quin/Mark BradyTel: +44 (0)203 368 3555

Broker

Beaufort Securities LimitedJon BellissTel: +44 (0) 20 7382 8300

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGCGDXGSGBGRL
Date   Source Headline
25th Mar 20217:00 amRNSInterim Results for Six Months to 31 December 2020
5th Mar 20212:00 pmRNSExercise of Warrants
3rd Mar 202112:22 pmRNSExercise of Warrants
12th Feb 202110:15 amRNSExercise of Warrants
4th Feb 20211:30 pmRNSExercise of Options
29th Jan 20217:00 amRNSDirectors’ Share Purchases
28th Jan 20214:41 pmRNSSecond Price Monitoring Extn
28th Jan 20214:36 pmRNSPrice Monitoring Extension
28th Jan 20211:46 pmRNSUpdates to Share Register and Exercise of Warrants
21st Jan 20219:57 amRNSPDMR Disclosures
15th Jan 202112:45 pmRNSSupport from Blue Chip Institutional Investors
14th Jan 202112:00 pmRNSSix Month Operations Update - H2 2020
12th Jan 20213:15 pmRNSExercise of Warrants
7th Jan 202111:00 amRNSTR-1: Notification of major holdings
6th Jan 20217:00 amRNSExercise of Warrants
17th Dec 20203:00 pmRNSTR-1: Notification of major holdings
10th Dec 20203:17 pmRNSTR-1: Notification of major holdings
7th Dec 20202:05 pmRNSSecond Price Monitoring Extn
7th Dec 20202:01 pmRNSPrice Monitoring Extension
7th Dec 20201:00 pmRNSExercise of Warrants
3rd Dec 202010:00 amRNSResults of AGM
16th Nov 20207:00 amRNSJubilee Live Interactive Webcast
10th Nov 20207:00 amRNSAudited results for the year ended 30 June 2020
5th Nov 20208:00 amRNSExecution of further copper tailings transactions
12th Oct 20207:00 amRNSQuarterly Operations Update Q3 2020
14th Sep 202012:30 pmRNSKabwe Mining Licence Renewed & Board Appointment
24th Aug 20207:00 amRNSNew Processing Agreement: Ore Beneficiation Plant
13th Aug 20207:00 amRNSChrome Operations Update
6th Aug 20207:00 amRNSFurther Copper Tailings Resource Secured in Zambia
13th Jul 20207:00 amRNSSix Month Operations Update
18th Jun 20207:00 amRNSLarge Copper Tailings Resources in Zambia Secured
19th May 202011:30 amRNSRelocation of chrome plant to maximise earnings
7th May 20202:00 pmRNSOperations Update in South Africa and Zambia
17th Apr 20209:15 amRNSUpdate: Operations during lockdown in South Africa
26th Mar 202010:10 amRNSUnaudited interim results
24th Mar 202011:33 amRNSSOUTH AFRICAN 21-DAY LOCKDOWN UPDATE
23rd Mar 20204:41 pmRNSSecond Price Monitoring Extn
23rd Mar 20204:37 pmRNSPrice Monitoring Extension
20th Mar 20204:47 pmRNSSecond Price Monitoring Extn
20th Mar 20204:42 pmRNSPrice Monitoring Extension
20th Mar 20202:05 pmRNSSecond Price Monitoring Extn
20th Mar 20202:00 pmRNSPrice Monitoring Extension
16th Mar 20204:42 pmRNSSecond Price Monitoring Extn
16th Mar 20204:37 pmRNSPrice Monitoring Extension
21st Feb 202010:10 amRNSDirector Dealing
28th Jan 20208:15 amRNSSix Monthly Operations Update
6th Dec 201912:45 pmRNSResults of AGM
3rd Dec 20197:00 amRNSDirector Dealing
25th Nov 20192:24 pmRNSTR-1: notification of major holdings
14th Nov 20191:15 pmRNSEquity Placing to Support Targeted Growth

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.