The next focusIR Investor Webinar takes place tomorrow with guest speakers from WS Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBHP Group Regulatory News (BHP)

Share Price Information for BHP Group (BHP)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 2,282.00
Bid: 2,284.00
Ask: 2,286.00
Change: -15.00 (-0.65%)
Spread: 2.00 (0.088%)
Open: 2,281.00
High: 2,300.00
Low: 2,277.00
Prev. Close: 2,297.00
BHP Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

2018 Global Metals Mining and Steel Conference

15 May 2018 12:58

RNS Number : 1541O
BHP Billiton PLC
15 May 2018
 

 

Issued by:

BHP Billiton Plc

 

Date:

15 May 2018

 

To:

London Stock Exchange

JSE Limited

 

For Release:

Immediately

 

Contact:

Helen Ratsey +44 (0) 20 7802 7540

 

 

BHP - 2018 Global Metals, Mining and Steel Conference Presentation

 

 

 

UK Listing Authority Submissions

 

The following document has today been submitted to the National Storage Mechanism and will shortly be available for inspection at www.hemscott.com/nsm.do:

 

· 2018 Global Metals, Mining and Steel Conference Presentation.

 

The document may also be accessed via BHP's website - bhp.com

 

 

 

 

NEWS RELEASE

 

Release Time

IMMEDIATE

Date

15 May 2018

 

Release Number

06/18

 

 

 

BHP delivering value and returns

 

BHP Chief Executive Officer, Andrew Mackenzie, today said the continued successful delivery of the Company's roadmap to grow long-term shareholder value, together with stronger commodity prices, has underpinned a significant increase in return on capital employed and delivered a 30 per cent increase in BHP's base value (1) over the past two years.

 

Speaking at the Bank of America Merrill Lynch Global Metals, Mining & Steel Conference in Florida, Mr Mackenzie said: "We have maximised operating cash flow as we have lowered costs through productivity; we have been disciplined and transparent in capital allocation; and we have identified new options to increase value and returns." 

 

Mr Mackenzie said over the past two years, through six key value drivers, BHP has:

 

· Reduced unit costs by more than 15 per cent;

· Accelerated our technology and innovation program;

· Progressed five high-return, latent capacity projects;

· Sanctioned two major projects in copper and oil;

· Made discoveries at four petroleum exploration prospects; and

· Improved the performance of our Onshore US acreage in preparation for exit into a supportive price environment.

 

"Alongside this, we have reduced net debt by over US$10 billion, returned US$8 billion to shareholders and, crucially, replenished our pipeline with new opportunities.

 

"This pipeline has the potential to add a further 40 per cent to the value of BHP, subject to our strict capital allocation processes."

 

Looking ahead, Mr Mackenzie said BHP:

 

· Continues to target a further US$2 billion in productivity gains by the end of the 2019 financial year, on top of the more than US$12 billion achieved since 2012;

· Would leverage its scale and simplicity to capitalise on the benefits of new technology to reinforce our position in safety and productivity and deliver a step-change in company performance;

· Has renewed its suite of latent capacity opportunities which have the potential to generate average returns in excess of 100 per cent;

· Continues to enhance its pipeline of future options, diversified across commodities and timeframes, which have an unrisked value of more than US$15 billion and the potential to deliver average returns of 17 per cent;

· Would continue to push its ongoing exploration program, focused on copper and petroleum, in line with favourable outlooks for these commodities; and

· Is making good progress with the exit from its Onshore US business, with the quality of acreage, higher oil prices, a lower US corporate tax rate and positive results from recent well trials all contributing to encouraging interest from potential bidders.

 

"BHP is set-up for future success. We have a simple, unique portfolio of the very best assets, diversified across attractive commodities.

 

"Our relentless pursuit of productivity, aided by a more agile and connected culture, will make sure we realise the full potential of our assets and capitalise on strong prices. On top of this, we have built an attractive suite of opportunities to drive further improvement. But, as always, we will remain disciplined in the allocation of capital with all investments weighed against cash returns to shareholders.

 

"Our path is deliberate, and we remain firm in our resolve to increase value and returns."

 

An audio-webcast of the presentation will be made available at: http://www.veracast.com/webcasts/baml/metalsmining2018/id57103254932.cfm

 

Further information on BHP can be found at: bhp.com

 

(1) Base value reflects planning forecasts (at consensus prices) before the addition of a broad suite of upside opportunities.

 

 

APPENDIX

 

The following information is included in Andrew Mackenzie's presentation slides.

 

Unit costs

Asset

Medium term1

WAIO

Conventional

Queensland Coal

~US$57/t

Escondida

 

Latent capacity

Options

IRR2

(%)

Risk3

(1-5)

Timing4

Capex

(US$m)

Description

WAIODebottlenecking

>100

Supply chain debottlenecking initiatives at the port and rail, and releasing latent capacity at Jimblebar to increase production to 290 Mtpa

EscondidaEWS Expansion

>50

●●

~500

Expansion of desalination plant to reduce groundwater usage and maximise concentrator throughput

EscondidaDebottlenecking

>100

●●

various

>500

Concentrator debottlenecking, sulphide leach reprocessing of ripios, truck and shovel fleet upgrades

SpenceRipios processing

~60

●●

2-5 years

250-500

Reprocessing of ripios dumped since the beginning of the Spence operations

Queensland CoalLatent capacity

>100

>5 years

>500

Investing in stripping capacity and pipeline of productivity initiatives to shift the bottleneck towards the coal handling plants

Olympic DamMaterial handling system

~20

>5 years

~500

Enabling project for BFX, extending materials handling system (MHS) into Southern Mine Area

SpenceDebottlenecking

>15

●●●

>5 years

>500

Processing lower grade hypogene material with increased recoveries, concentrator debottlenecking, in-pit semi mobile ore conveying

Average/aggregate

>100

~US$4 bn

Up to ~2 Mt of incremental Cu eq. capacity with~US$16 bn unrisked NPV

 

Future options

Options

IRR2

(%)

Risk3

(1-5)

Description

Atlantis Phase 3Petroleum

~25

Non-operated

Tie back to existing Atlantis facility unlocked through Advanced Seismic Imaging

Olympic Dam BFXCopper

~20

●●

Accelerated development into the Southern Mine Area, debottlenecking of existing surface infrastructure to increase production to 330 ktpa

ScarboroughPetroleum

>15

Non-operated

Tie back development to existing LNG facility

Wards WellMetallurgical Coal

~15

●●●●

Long-life, premium hard coking coal resource, greenfield underground longwall mine with proximity to existing operating assets

ResolutionCopper

~15

Non-operated

Underground block cave with attractive grade profile and competitive cost curve position

Jansen Stage 15Potash

~13

●●●

Tier 1 resource with operating costs of ~US$100/t (FOB Vancouver) and valuable expansion optionality

Jansen Stage 2-4Potash

~16

●●

Sequenced brownfield expansions of up to 12 Mtpa (4 Mtpa per stage)

Average/aggregate

~17

Aggregate unrisked value of ~US$15 bn spanning commoditiesand time periods

 

1. Based on an exchange rate of AUD/USD 0.75 and USD/CLP 663. Unit costs are in nominal terms.

2. Returns at 2018 analyst consensus price forecasts; ungeared, post-tax, nominal return.

3. Risk profile is based on a BHP assessment of each project against defined quantified and non-quantified risk metrics rated out of 5; 5 represents more risk.

4. Represents potential first production.

5. IRR is ~14% excluding the remaining investment for completion of the shafts and installation of essential service infrastructure and utilities.

 

 

Media Relations

 

Email: media.relations@bhpbilliton.com

Investor Relations

 

Email: investor.relations@bhpbilliton.com

Australia and Asia

 

Ben Pratt

Tel: +61 3 9609 3672 Mobile: +61 419 968 734

 

United Kingdom and South Africa

 

Neil Burrows

Tel: +44 20 7802 7484 Mobile: +44 7786 661 683

 

North America

 

Judy Dane

Tel: +1 713 961 8283 Mobile: +1 713 299 5342

Australia and Asia

 

Tara Dines

Tel: +61 3 9609 2222 Mobile: +61 499 249 005

 

United Kingdom and South Africa

 

Rob Clifford

Tel: +44 20 7802 4131 Mobile: +44 7788 308 844

 

Americas

 

James Wear

Tel: +1 713 993 3737 Mobile: +1 347 882 3011

BHP Billiton Limited ABN 49 004 028 077

LEI WZE1WSENV6JSZFK0JC28

Registered in Australia

Registered Office: Level 18, 171 Collins Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

BHP Billiton Plc Registration number 3196209

LEI 549300C116EOWV835768

Registered in England and Wales

Registered Office: Nova South, 160 Victoria Street

London SW1E 5LB United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

Members of the BHP Group which is

headquartered in Australia

 

Follow us on social media

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCFKPDPDBKDPPD
Date   Source Headline
13th May 20243:20 pmRNSForm 8.3 - BHP Group Limited
13th May 20243:16 pmRNSForm 8.3 - BHP GROUP LTD
13th May 20243:11 pmRNSForm 8.3 - BHP Group Limited
13th May 20243:03 pmRNSForm 8.3 - BHP Group Limited
13th May 20243:03 pmGNWInvesco Ltd: Form 8.3 - BHP Group Ltd Public dealing disclosure
13th May 20242:44 pmRNSForm 8.5 (EPT/RI)- Replacement of BHP Group
13th May 20242:44 pmRNSForm 8.3 - [BHP Group Ltd]
13th May 20242:43 pmRNSStatement re Revised Proposal from BHP
13th May 20242:39 pmRNSForm 8.3 - ANGLO AMERICAN PLC
13th May 20242:37 pmRNSForm 8.3 - BHP GROUP LTD
13th May 20242:34 pmRNSForm 8.3 - BHP Group Limited
13th May 20242:33 pmRNSForm 8.3 - BHP Group Limited
13th May 20242:28 pmRNSForm 8.3 - Anglo American plc
13th May 20242:25 pmRNSForm 8.3 - BHP Group Limited
13th May 20242:20 pmEQSForm 8.3 - The Vanguard Group, Inc.: BHP Group Limited
13th May 20242:12 pmRNSForm 8.3 - BHP Group Limited
13th May 20242:03 pmRNSForm 8.3 - Anglo American PLC
13th May 20241:06 pmRNSRevised Proposal for Anglo American plc
13th May 202412:01 pmRNSForm 8 (DD) - BHP Group Limited
13th May 202412:01 pmRNSForm 8 (DD) - BHP Group Limited
13th May 202411:56 amRNSForm 8.3 - BHP Group Ltd
13th May 202411:53 amRNSForm 8.5 (EPT/RI) - BHP Group Limited
13th May 202411:52 amRNSForm 8.3 - BHP Group Limited
13th May 202411:48 amRNSForm 8.5 (EPT/NON-RI) - BHP
13th May 202411:48 amPRNForm 8.3 - BHP Group Limited
13th May 202411:35 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 202411:16 amRNSForm 8.5 (EPT/RI) - BHP Group Limited
13th May 202411:08 amRNSForm 8.5 (EPT/NON-RI)
13th May 202411:08 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 202411:07 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 202410:46 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 202410:33 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 202410:30 amRNSForm 8.3 - BHP Group Limited
13th May 202410:22 amRNSForm 8.5 (EPT/RI) - BHP Group Limited
13th May 202410:21 amRNSForm 8.5 (EPT/RI) - BHP Group Limited Amendment
13th May 20249:49 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 20249:36 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 20249:36 amRNSForm 8.3 - BHP Group Ltd
13th May 20249:32 amRNSForm 8.5 (EPT/NON-RI) - BHP Group Limited
13th May 20248:34 amRNSForm 8.3 - BHP GROUP LTD/ANGLO AMERICAN PLC
13th May 20248:27 amRNSForm 8.5 (EPT/RI) - BHP Group Limited
13th May 20248:25 amRNSForm 8.5 (EPT/RI) - BHP Group Limited
13th May 20248:24 amRNSForm 8.5 (EPT/RI) - BHP Group Limited
13th May 20247:35 amRNSForm 8.3 - BHP Group Limited
13th May 20247:01 amRNSForm 8.3 - BHP Group Limited
10th May 20244:30 pmRNSForm 8.5 (EPT/RI)- Replacement of BHP Group
10th May 20244:22 pmRNSForm 8.5 (EPT/RI)- Replacement of BHP Group
10th May 20243:20 pmRNSForm 8.3 - BHP Group Limited
10th May 20243:09 pmRNSForm 8.3 - BHP Group Limited
10th May 20243:06 pmRNSForm 8.3 - BHP Group Ltd

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.