Cobus Loots, CEO of Pan African Resources, on delivering sector-leading returns for shareholders. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAFC Energy Regulatory News (AFC)

Share Price Information for AFC Energy (AFC)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 21.45
Bid: 20.90
Ask: 21.45
Change: -0.05 (-0.23%)
Spread: 0.55 (2.632%)
Open: 21.50
High: 22.00
Low: 21.30
Prev. Close: 21.50
AFC Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

KORE Fuel Cell System Achieves Operation

3 Aug 2015 07:00

RNS Number : 8106U
AFC Energy Plc
03 August 2015
 

3 August 2015

 

 

AFC Energy PLC

("AFC" or the "Company")

 

 

AFC's KORE Fuel Cell System Achieves Landmark Operation in Stade, Germany

 

 

Highlights

· Successfully commissioned and commenced operation of first KORE fuel cell system in Stade, Germany

· Historic Milestone 9 achieved - Phase-1 POWER-UP programme

· AFC still on target to achieve first full commercial scale operability of KORE module (final Milestone 11) in late 2015

 

 

AFC Energy plc (AFC.L), the industrial fuel cell power company, is pleased to announce that it has successfully commissioned and commenced operation of its first KORE fuel cell system in Stade, Germany.

 

This milestone marks the achievement of nearly a decade's investment in the AFC fuel cell system which, when fully operational in late 2015, will be the world's largest alkaline fuel cell system operating at an industrial facility selling power into the national electricity grid.

 

Following a week long commissioning of the fuel cell system at Stade, AFC's team on-site were able to affirm the safety and integrity of the system and introduced hydrogen into the fuel cells on Friday, 31 July 2015, to achieve a peak output of 7.56kW from a single operational cartridges (one of 24), with this cartridge intentionally operating at less than full capacity as envisaged within the POWER-UP commissioning programme. Importantly, when the original POWER-UP milestones were devised and announced to the market on 8 December 2014, the initial output target of the KORE by the end of July 2015 was set at 7.5kW to 15kW, however this was based on a forecast of two cartridges. To achieve this target with just one cartridge is great news for the technology.

 

The results reflect an historic achievement on two levels: firstly, not only AFC has delivered on its commitment to deliver a minimum 7.5kW from the system at the commencement of Phase 1 of the programme; but this achievement has been delivered within a timeframe (end of July 2015) which was arguably one of the most aggressive set within the Company's history and demonstrates the ability of the Company to deliver on its commitment to its shareholders and the market in general both as to time and cost.

 

The announcement marks achievement of Milestone 9 (of a total 11 Milestones) of the Status Update issued by AFC on 8 December 2014 (as set out in the Attachment below) and is the initial production of power on site with the associated testing prior to increasing power output in Phase 2. This milestone has been achieved with the cartridges validated by AFC in February 2015 at the required flow and operational settings.

 

This landmark achievement, executed in accordance with the ambitious timeline set in December 2014, gives AFC significant confidence in the upcoming commencement of Phase 2 of power generation on site. It will be following delivery of Phase 2, which was initially envisaged as commencing in Quarter 4 2015, but which now could be further accelerated, that AFC will commence selling power into the German grid through its Power Purchase Agreement (PPA) with Stadtwerke Stade (as announced on 27 July 2015).

 

This achievement further validates the prospect for long-term technical and commercial viability of the Company's alkaline fuel cell technology, whilst also establishing a positive precedent, in this prototype installation, that AFC's first major industrial project is on track to achieve its future significant milestones. Operational information pertaining to the fuel cell system will now be generated over the coming months for the further validation of the system both to AFC, and its international development, manufacturing and finance partners.

 

Mr Adam Bond, AFC's Chief Executive Officer, said: "Today marks one of the proudest moments in AFC's history. For the first time, the Company's research and development programme of the past decade has commenced commercial operations. This is a remarkable achievement delivered in record time and in a first class collaborative effort across all involved. On a personal level, I wish to extend my sincere thanks and congratulations to all the staff at AFC who have worked tirelessly and remained focussed over the past seven months on delivering something truly significant and establishing the platform for the commercialisation of this world leading alkaline fuel cell technology."

 

Mr Bond added, "It would be remiss of me to not also acknowledge the tireless efforts of our host partners, namely Air Products, and our contractors and sub-contractors in establishing not only the permitting and regulatory compliance of the system in Germany, but also delivering the civils, utilities, buildings and associated infrastructure for the KORE system at a remarkable pace in the face of many challenges."

For further information, please contact:

AFC Energy plc

Adam Bond (Chief Executive Officer)

 

 

+44 (0) 20 3697 1209

Zeus Capital Limited - Nominated Adviser and Joint Broker

Phil Walker, John Treacy

Alex Davies, John Goold  

 

+44 (0) 20 7533 7727

 

M C Peat & Co LLP - Joint Broker

Charlie Peat

 

+44 (0) 20 7104 2334

Lionsgate Communications - Public Relations

Jonathan Charles, Rachel Rigby

 

 

+44 (0) 7855 946972

 

 

 

 

 

 

 

 

About AFC Energy

 

AFC Energy plc is fast approaching commercialisation for its proven low-cost alkaline fuel cell system ("KORE"), which converts hydrogen into 'clean' electricity. AFC's key project POWER-UP will demonstrate the world's largest alkaline fuel cell system at Air Products' industrial gas plant in Stade, Germany. The date for the demonstration of the 240kW KORE system has been fast tracked to December 2015, representing the final phase of AFC's pre-commercialisation technical development programme and creating the platform for the Company's global commercial fuel cell deployment. For further information, please visit our website: www.afcenergy.com

 

 

 

 

Attachment

 

No.

Milestone

Timing

Status

1

Confirm that cartridges can achieve operating temperature using heat produced from fuel cell reactions -i.e. no external heat applied.

 

(KORE system start-up involves the cartridges self-heating until they achieve operating temperature).

Dec 2014

Achieved

2

Appoint engineering consultant to commence design package for POWER-UP programme in Stade, Germany

Dec 2014

Achieved

3

Commence operational performance monitoring of a 50 cell stack within an industrial gas plant environment. 

Jan 2015

Achieved

4

Commence operational performance monitoring of a 100 cell stack (up to 51 live cells) within the new KORE cartridge (first time), with this trial to take place within an industrial gas plant environment.

Feb / March 2015

Achieved

5

Commence construction of POWER-UP facilities, utilities and connections at Stade, Germany (subject to timely permitting and consents).

Feb 2015

Achieved

6

Conclude construction of POWER-UP facilities, utilities and connections at Stade, Germany.

 

 

May 2015

Achieved

7

Commence installation of POWER-UP KORE system at Stade, Germany.

May 2015

Achieved

8

Commissioning of POWER-UP KORE at Stade, Germany.

June 2015

Achieved

9

Commence Phase 1 - POWER-UP programme.

 

[Emphasis on initial production of power and associated testing prior to increasing power output in Phase 2]

July 2015

Achieved

10

Commence Phase 2 - POWER-UP programme

Q4 2015

In progress

11

Achieve first commercial scale operability of KORE module as part of POWER-UP programme

Dec 2015

In progress

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
STRLLFLVTTIFIIE
Date   Source Headline
14th Mar 20137:00 amRNSPosting of Annual Report and Accounts
27th Feb 20137:00 amRNSAFC Energy opens Korean Office
25th Feb 20137:00 amRNSAFC Energy ships fuel cell system to ICL
13th Feb 20137:00 amRNSFinal Results and Notice of AGM
12th Feb 20139:00 amRNSMPs learn about potential of fuel cells
12th Feb 20137:00 amRNSPresentation to Proactive Investors One2One Forum
30th Jan 20137:00 amRNSResearch relationship with Lancaster University
24th Jan 20137:00 amRNSAFC extends fuel cell electrode life beyond 6 mths
10th Jan 20137:00 amRNSDirectorate Change
17th Dec 20127:00 amRNSEU funding and acquisition
30th Nov 201211:36 amRNSTotal Voting Rights
8th Nov 20122:51 pmRNSIssue of Share Options and Warrants
7th Nov 20127:00 amRNSEU grant for UK fuel cell energy facility
31st Oct 201211:37 amRNSTotal Voting Rights
11th Oct 20127:00 amRNSEquity Investment of £8.7m by Strategic Investor
14th Sep 201211:54 amRNSAFC Energy Opens Pilot Production Plant
10th Sep 20127:00 amRNSLatest Independent Technology Review Highlights Pr
10th Aug 20123:04 pmRNSDirector Shareholding
31st Jul 20124:30 pmRNSTotal Voting Rights
27th Jul 20123:47 pmRNSExercise of Options
5th Jul 20127:00 amRNSInterim Results
25th Jun 20127:00 amRNSAFC & ICL to build UK's largest fuel cell facility
7th Jun 20127:00 amRNSAppointment of Broker
31st May 20127:00 amRNSDirectorate Change
23rd May 20127:00 amRNSAFC Energy appoints production facility manager
16th May 20127:00 amRNSAFC extends fuel cell electrode life beyond 3 mths
30th Apr 20124:30 pmRNSTotal Voting Rights
25th Apr 20123:41 pmRNSExercise of Options and Warrants
11th Apr 20124:10 pmRNSResult of AGM
11th Apr 20122:15 pmRNSCommercialisation agreement with Waste2Tricity
12th Mar 20125:30 pmRNSAFC Energy appoints Luther Pendragon
8th Mar 20126:03 pmRNSPosting of Annual Report and Accounts
8th Mar 20127:00 amRNSSir John Sunderland appointed to Board
7th Mar 20127:00 amRNSDirectorate Change
6th Mar 20127:00 amRNSAdditional Production Facility Investment Approved
5th Mar 20127:00 amRNSRepayment of Loan from Waste2Tricity
20th Feb 20127:00 amRNSPreliminary Results and Notice of AGM
13th Feb 20127:00 amRNSIndependent Technology Review
6th Feb 20127:00 amRNSNotice of Final Results
9th Jan 20127:00 amRNSGenerates First Industrial Power
1st Dec 20117:00 amRNSAward of Grant
7th Nov 20117:00 amRNSGrant of Options
21st Oct 20117:00 amRNSDirector Dealing
3rd Oct 20117:00 amRNSCommissioning of Beta Systems at AkzoNobel
22nd Sep 20117:00 amRNSAppointment of Non-Executive Director
11th Aug 20117:00 amRNSFirst commercial-scale system commissioned
8th Aug 20117:00 amRNSCompletion of HAZOP Study
29th Jul 20117:00 amRNSTotal Voting Rights
7th Jul 20117:00 amRNSInterim Results
4th Jul 20118:00 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.