RE: Hypothetical question8 Jul 2021 13:14
From RNS on 2nd FEBRUARY!!!!
"Greenfield Energy, Utah. Quadrise is still awaiting the receipt of oil samples at QRF from Greenfield Energy LLC ("Greenfield") as their programme for the start-up and commissioning of the Petroteq Oil Sands Plant ("POSP") at the Asphalt Ridge Facility in Utah, USA, was delayed and this work is still progressing. As previously noted, the availability of oil samples for testing at QRF is a critical path item on this programme, and sample testing will be completed within 2-3 weeks of receipt at QRF"
5 months + down the line and still no confirmation of receipt. So much for keeping us updated