RE: Prem30 Jul 2022 10:45
Hi Acker,
when the pilot mine was announced with a production date of end of March, there was some grace period before penalties kicked in. That was May - so knowing GR's history in delivering anything on time, I pencilled in May as a delivery date.
GR's suggestion (it isn't in a RNS) that mid February could be the delivery date just doesn't stack up for me- he's effectively said that they're already 6 weeks ahead of schedule. If it is now mid-February, he should publish that in a RNS along with an updated plan. I reckon that he would get some resistance from his team to doing that!
As I said, that latest interview smacked more of the old GR.