Commercial Production4 Nov 2024 09:12
During the quarter, 1,281,654 BCMs were mined at an average grade of 2.64 grams per ton
· Post-period, mining operation reaching c.30,000 BCMs per day and the commissioning of the fresh rock plant increasing the blending of high-grade fresh ore feed into the plant, which continues to operate at or above design.
The problems seem to be mining volumes Punter, not fundamental.
In Q3 they have achieved double the monthly average mined BCM, equal to 2.7m BCM, than they did per month in Q2.
For reference at Yani Q2 2021, they did 2.7m BCM, ave g/t 2.14 and produced 24.4k oz
All things being equal, Kouroussa should have done 15k minimum in Q3, perhaps 20k+