Future of megaprojects funded by JICA remains clouded
Authorities struggle to resolve issues with Japanese contractors
https://thefinancialexpress.com.bd/trade/future-of-megaprojects-funded-by-jica-remains-clouded
The Matarbari 2×600 MW Ultra Super Critical Coal-Fired Power Project, implemented at a cost of Tk 518.55 billion, has faced major operational problems since its commissioning in January this year, according to the meeting minutes.

Due to severe ash slagging and fouling in the boilers, power generation at both units has dropped by half, causing an estimated loss of $95.8 million, or around Tk 11.69 billion, in capacity payments, the project authorities informed the meeting.
To address the issue, a rectification plan worth Tk 1.35 billion has been proposed, requiring more than 21 months to complete it.
However, the Japanese-led joint-venture contractor has refused to bear the cost, citing the absence of relevant provisions in the contract. The contractor has also submitted a 15.69 per cent price escalation claim amounting to Tk 47 billion.