I think we just need to look at the bigger picture and just forget about Haverion for the time being and EG etc the company are going to spend over a quarters free cashflow on capex in the below to get as they state an extension to a multi year mine life! What then happens with Haverion that ultimately gets us to a 500k oz+ mine is for another day but for me the KEY is Telfer and what will drive the price in both the short term and medium term.
Telfer growth capital
Key life-extension growth capital investments at Telfer planned for FY26 include:
§ Pre-stripping of West Dome Open Pit Stage 7 Extension, expected to provide ore feed into FY29.
§ Purchase of new and the refurbishment of existing open pit fleet equipment, to support the targeted multi-year extension of open pit operations.
§ Underground life-extension development of the West Dome Underground, with more than 2,900 metres of growth development planned in FY26 (FY25: ~1,050 metres). Planned development includes the new ESC, which has returned encouraging drilling results in terms of width and grade as set out below.
§ Expansion of tailings capacity, including completion of TSF8 Stage 3 lift and substantially progress of the Stage 4 lift (collectively expected to provide capacity at current processing rates until approximately late FY28).
The increased growth capital investment relative to the previous 2-Year Outlook has been approved through the FY26 budgeting process, in light of the strong operating performance and resulting strong balance sheet of the group. The investments reflect the pursuit of further multi-year mine life extensions at Telfer beyond the previous outlook period, a key objective of Greatland's operating strategy.