RE: Commissioning17 Feb 2021 09:55
Looking at quotes from January's announcements, the big news we're all invested for is either imminent or we're all being shafted.
Dispatch/delivery announced at the start of the year . . .
RNS 5th Jan: "It is likely to arrive in Nottingham at the earliest on or about 8 January 2021, subject to any routine traffic or customs delays."
Let's say (most of) the machinery arrived on the 9th. One full working week later we get the following RNS, suggesting commissioning/testing was expected to take about a week . . .
RNS 18th Jan: "Assuming that commissioning proceeds as expected, the Company is working towards producing between 0.3m and 0.5m masks before the end of January" (production cannot start until the machine's signed off, and you don't produce c400,000 masks in a day so they must have been anticipating approx 7 days for set-up, allowing a few days for production.)
Then, of course not all of the machinery had arrived . . .
RNS 22nd Jan: "Commissioning of the machine at BioCity, Nottingham, commenced this week but is taking longer than anticipated, as parts have been delayed in transport from Spain, and will extend into early next week,"
So that 7-10 days of commissioning/testing couldn't start until (according to the RNS) roughly the 27th Jan.
Then the news . . .
RNS 1st Feb: " . . . without the Lemu engineers to assist in the completion of the commissioning of the machine, this will now be delayed until after their 10-day quarantine period has ended "
So by my estimates (and using RMS's RNSs) the commissioning/testing was expected to take around 7-10 days, has been delayed multiple times, but if quarantine started on 1st Feb for ten days then we should be on the brink of news in the next couple of days. Or we're on the receiving end of a hoax that'll have the FCA all over it.
I know which option I believe. It's frustrating, but I choose to hold for a big positive RNS in the next few days, followed by another one a few days later with confirmed orders on it.