RE: Q1 results13 Apr 2022 06:46
Apologies for an earlier post where I incorrectly said that BELCO was part of BE. The information below taken from last year’s Updates seems to confirm that BELCO is part of the Bushveld Vanadium platform, just as Lindon pointed out from information published by BMN.
I wish BMN would keep their website up to date!
Q1 2021 Update
(Under Bushveld Vanadium)
“The procurement phase of the Bushveld Electrolyte Plant has commenced, with commissioning expected in H2 2022.”
And:
“Bushveld Electrolyte Company
§ The development of the 200MWh electrolyte manufacturing plant is progressing according to plan. The remaining environmental permits and safety risk assessments were successfully applied for and conducted respectively during Q1 2021.
§ The procurement phase of the Bushveld Electrolyte Plant has commenced with the ordering of major long lead items. The signing of the lease agreement with the Industrial Development Zone in East London and ground-breaking for the construction of the property is due to occur during Q2 2021, while the installation of major equipment is planned for during Q3 2021. Commissioning of the plant is expected in H2 2022.
§ Including the ZAR36 million spent to date (approximately US$2.1 million), capital expenditure for the construction of the electrolyte plant has been revised to ZAR217 million (approximately US$13.6 million), originally US$10 million.
§ Bushveld's capital expenditure investment commitment for plant construction has been amended to ZAR81 million (approximately US$5.1 million) through 2024. The remaining balance of ZAR136 million (approximately US$8.5 million) will be funded through equity and debt instruments in terms of the agreement signed between Bushveld Energy and its partner, the Industrial Development Corporation of South Africa.
§ As the project progresses into procurement and construction, Bushveld will transfer its interest in the electrolyte manufacturing plant company, Bushveld Electrolyte Company, to its vanadium production operations, alongside Vametco and Vanchem.”
Q2 2021 Update
No mention at all of BELCO, electrolye plant or anything related. Remember this is essentially an update of Bushveld Vanadium activities!
Q3 2021 Update
No mention at all of BELCO, electrolye plant or anything related.
Q4 2021 Update
Group Capital Expenditure
(Includes the following entries:)
Bushveld Electrolyte Company ("BELCO") ZAR37 million (circa US$2.4 million)
Bushveld Energy ZAR10 million (circa US$0.7 million)
(Edit: note that BELCO and BE listed separately!)
So it would seem that the intention to transfer BELCO to the Bushveld Vanadium platform was carried out as can be deduced from Q1and Q4 Updates.