RE: The interview19 Dec 2022 15:08
Now with everyone's indulgence. I want to turn the attention to the contractors. What is their remit?
My thoughts are that the design, manufacture and testing of the DMG gasification and associated parts are all to be factory built offsite. And is really part and parcel under PHEs control. Is that one of the contractors mentioned.
Then there is the onsite fabrication of roadways and buildings to house the DMG plant. Now that in my mind is suitable for SISK to carry out. After all they already have the setup and heavy plant available. And are proven, roadway, bridge and services contractors.
Could they also be capable of coordinating along with Peel to carry out those works including contracting out the weighbridge, gas tanks, plastic feedstock silos, electrical intake rooms and of course the 5-gas turbine electrical generators.
Then finally comes the installation of the DMG thermal plant. Would that come under the manufacture’s own installation team?
I am beginning to think that the two thirds sized, close to commercial operating plant that is the be located somewhere else is going to be our FOAK commercial installation.
Please fill free to offer any other thoughts on the matter. Plus, as a retired electrical engineer and company director of the two business I built from scratch. I have to admit I am a bit of a Geek myself.
So, nothing wrong with KR in my mind. It’s just that we don’t always make good salesmen or should I say, persons to avoid offending the woke’s.