As per RNS Q1 / Q2 work schedule it does look that everything, if it goes according to plan, will be ready by the end of Q2 with the drilling rig on site and all relevant service companies. Therefore assuming the service personnel will not be standing idle just admiring the rig and with a fair wind, drilling may be at the start of Q3, July, rather than the end, Sep. The drill is expected to take 50 days so it is possible we could also have the drill results in Q3, albeit the latter end.
Completion Date
Activity
Q1 2026 (JAN - MAR)
Order long lead items such as wellhead/casing
Tender & contract drilling rig (currently 4 appropriate rigs available)
Q2 2026 (APR - JUN)
Water bore(s) drilling and installation on site
Surface conductor pipe installation comprising the first section of drill casing
Service company tender & contract; includes cementing, mud logging, e-logging, WSG, testing contractors
Expand site/access roads, airstrip, drilling pad works. Inspection, planning and costing already completed
Finalise the engineering and well design in conjunction with the drill contractor
Mobilise drilling rig to site and all relevant service companies