Review of current position28 Aug 2021 07:52
HE1 started trading in December at 4.25p and had £6m which was earmarked for 2D Seismic infill and drilling 3 wells
From January to end of March it traded between 6.8p-8.2p
In March we started the 150km 2D Seismic exercise (later extended to 200km)
Mid April we had a 10p Placing for £10m (SP had risen to 12p (briefly at 14p))
Having these funds enabled them to contract the current drill rig (capable of appraisal drilling). It also covered a 3D seismic programme and feasibility study of any discovery. As we have no discovery, it is now being used for more seismic (and possibly some drills). The SP and strategy almost mirror where we started from in January with the SP currently bouncing around 8p-9p.
We have information from the 200km of 2D Seismic, knowledge of the Tai stratigraphy and a better understanding of the drills required for both the shallower and deeper depths. Unfortunately we don't have any wireline data for the shallower and deeper depths. We only have that data from 880m to 400m (potentially) where the Tai-1 casing ended. We know that the Helium will rise from lower depths, but not move laterally at shallow depths, and that an efficient seal is not required for it to be effective. We were also unable to perform a Drill Stem Test to capture any samples.
From the admission document, the following costs can be referenced :
Working Capital and General & Administration expenses (G&A) £2,157,710
Infill 2D seismic work £692,300 (This was originally 100km-125km but ended up at 200km so possibly £1m?)
Licence fees £569,230 (We will need new permits for the 2D. We have some drilling licences but will more be required?)
Fieldwork £192,300
Drilling £1,461,540 (Originally 3 holes - the current rig was around £1m per hole but Tai-1 ran to around £1.4m)
Well evaluation £276,920
The Costs for work on discovery were estimated to be :
Appraisal well drilling: £2.4 million
Enhanced well completion: £0.5 million
3D seismic programme: £3.8 million
Feasibility Studies and licence fees: £1.2 million
Additional operational contingencies, working capital and expenses: £2.1 million
We don't know the extent of the seismic work that will be undertaken and we will require permits before that can start as well as arranging for the equipment, contracting etc. We have not been given any information on whether shallow drilling will be going ahead this year. If it does, I am not sure we have data to suggest that a discovery could be made from it. If we so drill, will we be testing different trap types as per the initial plan, or was there enough detail extracted from what was found at Tai-1? DM mentioned that for the cost of 1 O&G well they were able to drill 3 Helium wells which suggests if an O&G rig is required, the funds required could be substantial.
Hopefully we get some clarification soon, but right now it seems there will be a few months before anything really happens.