RE: WATER FRAMEWORK COMPLIANCE ASSESSMENT posted8 Jan 2020 18:50
“ The current treated effluent concentrations levels are at or above threshold levels at the point source. Precise details of the effluent outfall and its associated concentration levels will be clarified as part of the ongoing environmental permitting process, development design and dispersion modelling minimising the risk of pollution of waters and degradation of habitats.”
The EA response to the above statement from Ezygo could go two ways:
1) the response could be accepted and a condition is put on the planning permission approval.
2) the EA could insist that the required engineering is carried out (work which should have been done anyway) in order to determine the effluent details and therefore approve (or not) the submission with no related condition.
If it’s 1), we’ll be looking at 4 weeks until determination. If 2) it could be 2+ months, particularly as this will require significant spend.