RE: Major Drilling - on track7 May 2023 12:47
TMK First drill was started April 12th, finished April 26th - so 14 days. Took 9 days to move and set up and start 2nd drill, so if we say the same happens, the 2nd drill should finish May 19th, another 9 days to move and set up 3rd drill, so 3rd drill should finish June 11th. As said that's if all run the same sequence as the first drill . It then depends how long to move the drill from TMK's block to Velociraptor. I believe it is a fair trek, and then to set the drill up and start on Velociraptor, so i would say last week in June potentially