RE: Today's RNS23 Nov 2018 08:40
So yes no EGM without the License Extension but let's assume that we get the "circular"on the 30th November, the EGM would not be likely before the week beginning 17th December and therefore Shareholder ratification that week. That would allow the Zubairs and AEX no more than 4 days to get the Farm-Out concluded, TPDC approval and a contract in place for the rig before the Tanzanian Parliament go into recess from the 21st to the 7th January.... I simply do not think this is feasible.
Moreover, I believe that the movement of the long stop out to the 31st March is simply an indication of the two parties recognising and accepting this reality.... I think January at the very best for Farm-Out completion and that assumes we get the License extension before the recess starts.
In any event there will be no C1 spud this year!!