RE: Build times for energy solutions?25 Feb 2020 11:57
Hi Slinkyfink
In my experience, it isn’t so much the build time for the energy solutions but more the time taken for the various permitting and contracting (environmental impact assessments, grid connection licences, land rights for leeways, PPAs, etc.) Apologies if this is stating the obvious. The ease or difficulty is going to vary wildly, but there is so much market to go after which makes it so exciting. Path-of-least-resistance projects should really build momentum for the technology.
For me, the most attractive use of VRFBs is the bolt-on to built wind and PV sites. However, permitting can still be needed here if there is grid connection involved. I believe this may have been looked into for companies like the Ventus VCTs (VEN, VEN2, VNC, VENC), where I’m invested (and which have regularly paid a 7% tax-free dividend, he added shamelessly!) This type of asset would be a perfect fit for VRFBs.