RE: RNS20 May 2022 09:47
Solid Update ... was expecting some production but as per Q4'21 Ops Report it looks like Processing Plant is offline whilst planned upgrades progress & only gold 'Sales' of 1,047ozs reported.
Phenomenal progress all the same across 2 of 3 fronts whilst acquisition development plans progress:
1) Kilimapesa Infill & Expansion Drilling = increased resources, JORC category confidence & Life Of Mine
> 2022 Programme Plan = 3,000m DD and 12,000m RC drilling at Kilimapesa & "Aiming to increase the overall project resource from 670,000oz to >2Moz" up from 1.5Moz target in Q4 report
> Q1, 35x RC holes @3,420m have been drilled "400m to the east of active underground mining and opencast pit"
> Q1, 5x DD holes @871m "to determine both the strike & the down-dip extent of mineralisation" on Kili Hill
> Q1, 7x DD holes @157m underground in Adit D at Kili Hill
> RNS @12-May-22 "Assay results for the first 27 RC holes (KPGRC 005-KPGRC 032) have been received" & "Updated resource from the Kilimapesa Hill deposit expected at the end of Q2 2022" grades inline with nearby producing mine
> RNS @12-May-22 reported "52 holes (5,194m) of RC drilling completed" & "Six holes (1,241m) of DD drilling" .... discrepancy needs clarifying as 12-May-22 RNS higher than Q1 Ops report totals !
2) Process Plant Expansion & Upgrades
> RNS @9-Feb-22 "Work on the milling circuit expansion will also commence through installation of the second ball mill, which is currently in Nairobi and scheduled to be refurbished. In addition, work on the new crushing and screening plant and upgrades to the thickeners, cyclones and installation of additional CIL tanks will also commence."
> Heap Leach - 1 of 4 pads @5kt/month throughput commissioned end Mar-22 @53.2% efficiency
> Heap Leach Pilot plant completion target end Q2 versus 20kt overall production capacity whilst each pad capacity stated as 7.5kt
3) Acquisitions:
> Updates on Nyakafuru and Simba projects, Nyakafuru Reefs JORC expansion and mine costs need updating
Commentary:
Q1 Ops report contains almost no operational mining throughput, processing or recovery information which implies large scale shutdown of processing plant as upgrades and expansion are implemented especially as gold sales were quoted and not gold produced.
Heap Leach Plant - development of Pilot, individual 7.5kt pad capacity versus planned 5kt throughput needs clarifying as implies throughput once all 4 pads commissioned maybe higher than 20kt/month.
Updated MRE with revised target of 2Moz at Kilimapesa versus 1.5Moz stated in Q4 Ops Report should be interesting