RE: Spud date please4 Oct 2022 17:02
Here’s an RNS from Oct last year.
“APT, the operator, has confirmed that mobilisation of the seismic team has commenced, and the first phase of the seismic shoot will begin on 15 November 2021. The team will then complete the second phase of the seismic shoot in Q1 2022 after the Tanzanian rainy season. The Chikumbi-1 well is expected to commence drilling in Q3 2022.”
So the Seismics are 9 months behind schedule, so how is Ch-1 spud only 3 months behind schedule?