RE: Timing of rise18 Jun 2024 09:17
For me the contract will be signed at some point soon. Both sides have been committed since the Revised agreement with SEPCO (8/8/2023). The more interesting question is what we will get in this new EPC. IMHO there are two key aspects:-
Firstly, what comes next? When Potash prices were higher there was talk about DX following Kola. DX, as currently planned, has a negative NPV at current Potash prices. I suspect that we might get a phase 2 planned at Kola where (Potash prices permitting) the project scale goes up to 4 M/T per annum after additional CapEx (like Jansen). A phase 2 project could add 80% of phase 1's NPV.
Secondly, what are the significant changes to the mining plan and how much improvement in NPV is achieved? There are many possibilities here, for example:
Will the technology change significantly (from underground mining to directional drilling for example)?
What will be mined? In the original plan only the Sylvanite is mined at Kola. Will the new plan mine the Carnallite also?