Viura Field Update

29 Apr 2025 16:42

RNS Number : 6854G
Prospex Energy PLC
29 April 2025
 

 

Prospex Energy plc / Index: AIM / Epic: PXEN / Sector: Oil and Gas

 

The following amendment has been made to the '(Viura Field Update)' announcement released on (29th April) at (7:00) under RNS No 5079G.

 

(Total natural gas produced from the Viura-1B well from start-up in December 2024 to the end of Q1-2025 was 30.2 MMscm = 1.1 Bcf (which is ≈ 4.4 MMscm = 154 MMscf net to Prospex)).

 

All other details remain unchanged.

The full amended text is shown below.

 

29 April 2025

 

Prospex Energy plc

("Prospex" or the "Company")

 

Viura Field Update

 

Prospex Energy plc (AIM: PXEN), the AIM quoted investing company focused on European gas and power projects, wishes to inform shareholders that it has been advised by the Operator of the Viura field, HEYCO Energia Iberia S.L. ("HEI" or the "Operator"), of the temporary cessation of production of the new Viura-1B well due to a leak in the completion tubing. The Operator is sourcing the necessary equipment including mobilising a suitable drill rig to perform the workover with the aim of reinstating production from the field by mid-June 2025. Although this is a temporary halt to production, it will have an impact on the stated schedule for drilling the development wells, which is now anticipated to take place next year.

 

Prospex owns 7.24% of the Viura field through its ownership of 7.5% of HEYCO Energy Iberia S.L. ("HEI" or the "Operator"). Prospex is accruing 14.47% of the production income from the Viura gas field until payback of its capital investment (expected to be ≈£8 million) plus the accrued 10% p.a. interest thereon.

 

Mark Routh, Prospex's CEO, commented:

"This is an unfortunate temporary cessation of production at Viura while the operator mobilises the necessary equipment to carry out the required interventions and workovers to re-establish stable gas production from the Viura gas field.

"It is important to re-establish stable gas rates from Viura before the drilling of the new development wells commences in order to optimise the financing options for phase 2 of the development drilling campaign. We have every confidence in the Operator, who can access state-of-the-art technologies and expertise both in country and from the USA, to deliver the optimum outcome of the workover interventions and more importantly the future development well drilling. One benefit arising from the disruption to production at the field and the resultant delay to the development drilling it is that it provides Prospex with more time to generate cash from its other producing assets and fund our share of expenditure at Viura reducing the need to source additional funding from the market.

"I will keep shareholders updated with regular progress reports as the well interventions proceed."

 

Background

The Viura-1B well is currently not in production and was shut in during April-2025 owing to a leak in the completion tubing which requires a rig intervention to reinstate production. The Operator is now sourcing the necessary equipment including mobilising a suitable drilling rig in order to perform the workover by mid-June 2025.

Total natural gas produced from the Viura-1B well from start-up in December 2024 to the end of Q1-2025 was 30.2 MMscm = 1.1 Bcf (which is ≈ 4.4 MMscm = 154 MMscf net to Prospex).

Whilst the rig is on site in June-2025 the Operator also plans a workover on the original producing well, Viura‑1ST3 which is not currently in production. The Viura‑1ST3 workover is in order to shut off a water zone to prevent produced water ingress from deeper in the reservoir flowing to the top producing zones in the new well Viura-1B. Decreasing water production into the processing plant will reduce operational costs. Following this workover the Viura‑1ST3 well will not produce gas without further intervention. As advised in the RNS of 8 April 2025, the Viura-3 water injection well is capped and suspended as it has been deemed unsuitable for water injection.

As a result of these necessary workovers, the schedule of drilling the Phase 2 wells Viura-3A and Viura‑3B has been pushed back to 2026. This will allow further time for the Operator to procure the necessary equipment and to optimise the 3D seismic reprocessing and reinterpretation to fine-tune the subsurface well locations of these development wells.

The Operator will recommence negotiations with the syndicate of banks to provide debt-finance towards the cost of drilling the development wells upon the resumption of production from well Viura‑1B.

The Operator is also planning to test in Q1-2026 the hitherto untested Utrillas-B reservoir, which sits below the main Utrillas-A reservoir horizon and which was identified as containing the presence of gas bearing reservoir quality sandstones in December 2024.

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation (EU) No. 596/2014 as it forms part of United Kingdom domestic law by virtue of the European Union (Withdrawal) Act 2018, as amended by virtue of the Market Abuse (Amendment) (EU Exit) Regulations 2019.

 

* * ENDS * *

For further information visit www.prospex.energy or contact the following:

 

Mark Routh

Prospex Energy PLC

Tel: +44 (0) 20 7236 1177

Ritchie BalmerRory Murphy

Strand Hanson Limited

Tel: +44 (0) 20 7409 3494

Andrew Monk (Corporate Broking)Andrew Raca (Corporate Finance)

VSA Capital Limited

Tel: +44 (0) 20 3005 5000

Neil Passmore

Leif Powis

Hannam & Partners

Tel: +44 (0) 20 7907 8500

Ana Ribeiro / Charlotte Page

St Brides Partners Limited 

Tel: +44 (0) 20 7236 1177

 

Notes

Prospex Energy PLC is an AIM quoted investment company focussed on high impact onshore and shallow offshore European opportunities with short timelines to production. The Company's strategy is to acquire undervalued projects with multiple, tangible value trigger points that can be realised within 12 months of acquisition and then applying low-cost re-evaluation techniques to identify and de-risk prospects. The Company will rapidly scale up gas production in the short term to generate internal revenues that can then be deployed to develop the asset base and increase production further.

 

Qualified Person Signoff

In accordance with the AIM note for Mining and Oil and Gas Companies, the Company discloses that Mark Routh, the CEO and a director of Prospex Energy plc has reviewed the technical information contained herein. Mark Routh has an MSc in Petroleum Engineering and has been a member of the Society of Petroleum Engineers since 1985. He has more than 40 years of operating experience in the upstream oil and gas industry. Mark Routh consents to the inclusion of the information in the form and context in which it appears.

Glossary:

Bcf Billion standard cubic feet

Bcm Billion standard cubic metres

Boe Barrels of Oil Equivalent (where 1 MMBoe = 5.8 Bcf)

MMBoe Million Barrels of Oil Equivalent

mcf Thousand standard cubic feet

MMscfd Million standard cubic feet per day

MMscm Million standard cubic metres

MMscm/d Million standard cubic metres per day

MWh Mega Watt hour

scm Standard cubic metres

scm/d Standard cubic metres per day

TTF The 'Title Transfer Facility' - a virtual trading point for natural gas in the Netherlands.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBUGDSIXDDGUC
Date   Source Headline
1st Jun 20267:00 amRNSStrategic Collaboration with IMMAGE
28th May 20267:00 amRNSFinal Results & Notice of AGM
15th May 20267:00 amRNSQ1 2026 Overview &Unaudited Group Financial Update
7th May 20267:00 amRNSBoard Changes
30th Apr 20267:00 amRNSItaly Selva Malvezzi - Q1 2026 Activity Report
22nd Apr 20267:00 amRNSDunajec Licence Award, Poland
1st Apr 20267:00 amRNSSan Licence Award, Poland
26th Mar 20262:50 pmRNSCorporate Update & New Corporate Presentation
24th Mar 20267:00 amRNSFormal Offer of onshore Polish licences
18th Mar 20267:00 amRNSTotal CLN Funding Reaches £2m, 25% Above Target
17th Mar 202610:30 amRNSConversion of Loan Notes and TVR
13th Mar 20267:00 amRNSUpdate: £1.6 million CLN Fundraise Oversubscribed
13th Mar 20267:00 amRNSUpdate: £1.6 million CLN Fundraise Oversubscribed
12th Mar 20267:00 amRNSLetter to Shareholders and IMC Investor Event
16th Feb 20267:00 amRNSTarba - El Romeral Production Re-start
2nd Feb 20267:00 amRNSCEO takes up post
28th Jan 20267:00 amRNSItaly: Selva Malvezzi Production Concession
22nd Jan 20267:00 amRNSRental of Transformer at El Romeral
19th Jan 20267:00 amRNSCompletion of Convertible Loan Notes Fundraise
12th Jan 20267:00 amRNSUpdate: Convertible Loan Notes Fundraise
6th Jan 20267:00 amRNSSenior Management Changes: Appointment of New CEO
19th Dec 20257:00 amRNS£565,000 Issuance of Convertible Loan Notes
19th Dec 20257:00 amRNS£565,000 Issuance of Convertible Loan Notes
4th Dec 20257:03 amRNSItaly: Selva Malvezzi – Operational Update
24th Nov 20257:00 amRNSThird Quarter Unaudited Group Financial Update
20th Nov 202511:51 amRNSViura Operational Update
18th Nov 20257:31 amRNSItaly: Selva Malvezzi Production Concession Update
17th Nov 20257:00 amRNSCompletion of Statutory EIA Consultation Process
31st Oct 20257:00 amRNSItaly: Selva Malvezzi - Q3 2025 Activity Report
24th Oct 20257:00 amRNSPlateau Production Rates confirmed at Viura Field
22nd Oct 20257:00 amRNSProspex Advances European Growth Strategy
20th Oct 20257:00 amRNSProduction Restarts at Viura Field
17th Sep 20257:00 amRNSViura Field Update
10th Sep 20257:00 amRNSHalf-year Report
26th Aug 20257:00 amRNSViura Field Update
21st Aug 20257:00 amRNSSigning Gas Sales Agreement with Hera Group
31st Jul 20257:00 amRNSOperational Update
30th Jun 20257:00 amRNSResult of Retail Offer and Additional Subscription
27th Jun 20257:00 amRNSWRAP Retail Offer Still Open
25th Jun 20251:01 pmRNSResult of AGM
25th Jun 20257:01 amRNSWRAP Retail Offer for up to £500,000
25th Jun 20257:00 amRNSResult of oversubscribed Placing and Subscription
24th Jun 20255:08 pmRNSProposed Placing & Subscription and Retail Offer
20th Jun 20257:00 amRNSAGM Proceedings
9th Jun 20257:00 amRNSViura Field - Planned Reinstatement of Production
30th May 20257:00 amRNSChange of Registered Office
27th May 20257:00 amRNSFinal Results
2nd May 20257:00 amRNSQ1 2025 Activity Report
29th Apr 20254:42 pmRNSViura Field Update
29th Apr 20257:00 amRNSViura Field Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.