The next focusIR Investor Webinar takes place tomorrow with guest speakers from WS Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksPensana Plc Regulatory News (PRE)

Share Price Information for Pensana Plc (PRE)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 24.00
Bid: 23.30
Ask: 24.20
Change: 0.70 (3.00%)
Spread: 0.90 (3.863%)
Open: 23.40
High: 24.00
Low: 23.40
Prev. Close: 23.30
PRE Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Longonjo Project Update

4 Mar 2024 07:00

Pensana Plc - Longonjo Project Update

Pensana Plc - Longonjo Project Update

PR Newswire

LONDON, United Kingdom, March 04

 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION

 

Pensana Plc

 

Long lead items orders placed and site preparation works well underway at Longonjo

 

Pensana (PRE.L) (the Company) is pleased to provide the following update on the Longonjo project:

 

 

Concrete foundations have been poured for the 316-person modular camp manufactured in South Africa for despatch to site later this month.The on-site team, under the leadership of experienced Project Manager Kevin Botha, is continuing to make good progress with preparatory works ahead of main construction anticipated in May 2024, with cold commissioning commencing in August 2025.

 

An order has been placed with NCP International, a global supplier of new and refurbished comminution equipment based in South Africa, for the US$2.3 million ball mill for delivery from Johannesburg to meet the construction and commissioning timelines for the concentrator plant.

 

The detailed design and procurement documentation for other main long lead time or critical path items, such as the thickeners and flotation columns in the concentrator section, along with key equipment in the recovery/MREC section, such as the sulphuric acid plant, have been completed and orders will be placed with the selected vendors shortly.

 

Grupo Nov has completed the civils and services connections for the initial section of the 316-person modular construction camp. The US$1.3 million camp has been fabricated off site and is ready for shipment from Johannesburg to site during March 2024.

 

All the site access roads have been completed within the licence area. The 5,000-litre potable water tank is ready for installation to support the construction camp and the future plant facilities.

 

High priority is being given to community relations and in particular to the resettlement action and livelihoods restoration plans which are progressing according to plan and are being well received.

 

The agricultural demonstration plots are in their second year and continue to generate excellent baseline data. They are providing the opportunity to train local farmers in the latest agricultural methods.

 

The mine and processing plant will be constructed from May 2024 and commissioning of the various circuits will commence in March 2025 and continue until final commissioning in April 2026.

 

A schedule of the expenditures is set out below.

 

Quarterly Expenditures

US Dollars

Activity

May - July 2024

         5 044 000

Civil and Earth Works

August – October 2024

       18 889 000

Structural and Mechanical installation

November – January 2025

       32 435 000

Platework and piping installation

February – April 2025

       36 032 000

Electrical installation

May -July 2025

       36 185 000

Instrumentation installation

August – October 2025

       38 274 000

Cold Commissioning

November – January 2026

       23 096 000

Hot Commissioning

February – April 2026

6 476 000

Final Commissioning

Total

     196 432 000

 

 

Tim George CEO commented: The growing on-site team, supported by experienced contractor Grupo Nov, is fully operational and is well advanced with the earth works and other preparatory works ahead of the commencement of the main civils and earthworks campaigns in the weeks ahead.

 

We are particularly pleased with the attention to health and safety, environmental performance, the training completed on site and the continued focus on the community engagement programs. This will continue to be a priority as we build out the workforce which will increase to over 650 people on site at peak construction later this year.”  

About Longonjo

 

The electrification of motive power through Electric Vehicles and Wind Turbines is the biggest energy transition in history and is forecast to generate a demand growth for magnet metal NdPr of 7.5% CAGR over the next decade.

 

Pensana owns one of the world's largest undeveloped rare earth mines, and one of only three with a JORC Reserve greater than 100,000 tonnes of NdPr.

 

Pensana recently announced that one of its major potential customers has approved the product qualification specifications for Longonjo’s proposed MREC product. The Longonjo MREC contains 50% Total Rare Earth Oxide of which 24% is NdPr with minimal impurities and is radionuclide-free.

 

Longonjo is expected to produce 20,000 tonnes of MREC commencing 2026 and 40,000 tonnes of MREC from 2029 onwards following the planned expansion.

 

At full production Longonjo will produce ~5% of world production of NdPr in the form of an exported mixed rare earth carbonate.

 

The upfront capital cost of US$217 million for the fully permitted mine and processing facilities is amongst the lowest amongst its peers.

 

The information contained within this announcement is considered by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No.596/2014. Upon the publication of this announcement via a Regulatory Information Service, this inside information will be considered to be in the public domain. The person responsible for arranging for the release of this announcement on behalf of the Company is Paul Atherley, Chairman.

 

- ENDS –

 

For further information, please contact:

 

Shareholder/analyst enquiries:

Pensana Plc 

Paul Atherley, Chairman IR@pensana.co.uk

Tim George, Chief Executive Officer

Rob Kaplan, Chief Financial Officer

 

 

 

 

 



Date   Source Headline
29th Jan 20217:00 amRNSQuarterly Activities and Cashflow Report
28th Jan 20217:00 amRNSRemote Access to General Meeting
25th Jan 20217:00 amRNSSaltend Planning Application
22nd Jan 20217:00 amRNSNotice of General Meeting
22nd Jan 20217:00 amRNSVoluntary Delisting From ASX
20th Jan 20217:00 amRNSVoluntary Delisting From ASX
18th Jan 20217:07 amRNSVoluntary Delisting From ASX
4th Jan 20217:00 amRNSAdmission of shares
21st Dec 20207:00 amRNSHigh grade rare earths confirmed at Coola
7th Dec 20207:00 amRNSSite selected for rare earth processing facility
30th Nov 202010:40 amRNSRESULTS OF ANNUAL GENERAL MEETING
23rd Nov 20207:00 amRNSAppointment of Liberum as Joint Broker
18th Nov 20209:19 amRNSRemote Access to Annual General Meeting
16th Nov 20207:00 amRNSBFS Update
13th Nov 20202:06 pmRNSSecond Price Monitoring Extn
13th Nov 20202:01 pmRNSPrice Monitoring Extension
9th Nov 202011:06 amRNSSecond Price Monitoring Extn
9th Nov 202011:00 amRNSPrice Monitoring Extension
9th Nov 20209:05 amRNSSecond Price Monitoring Extn
9th Nov 20209:00 amRNSPrice Monitoring Extension
6th Nov 20207:00 amRNSNotice of Annual General Meeting
2nd Nov 20207:00 amRNSAppointment of Rt.Hon.Baroness Northover PC as NED
30th Oct 20207:00 amRNSQuarterly Activities and Cashflow Report
19th Oct 20207:00 amRNSCoola exploration programmes in full swing
16th Oct 20204:40 pmRNSSecond Price Monitoring Extn
16th Oct 20204:35 pmRNSPrice Monitoring Extension
16th Oct 20202:05 pmRNSSecond Price Monitoring Extn
16th Oct 20202:00 pmRNSPrice Monitoring Extension
12th Oct 20207:00 amRNSStudy into UK based Rare Earth processing facility
9th Oct 20207:00 amRNSDirectorate change
5th Oct 20207:00 amRNSSuccessful development of MREC flow sheet
1st Oct 20207:00 amRNSReleased of 2020 Annual Report
25th Sep 20205:28 pmRNSIssue of equity to Angolan Sovereign Wealth Fund
21st Sep 20202:01 pmRNSPrice Monitoring Extension
21st Sep 20207:00 amRNSRoyalty over Tanzania gold exploration assets
14th Sep 20207:00 amRNSLongonjo Mineral Resource estimate upgraded
12th Aug 20207:43 amRNSAppointment of Broker and Company Secretaries
11th Aug 20209:31 amRNSAdmission of shares
10th Aug 202011:06 amRNSSecond Price Monitoring Extn
10th Aug 202011:00 amRNSPrice Monitoring Extension
10th Aug 20207:00 amRNSAppointment of an Non-Executive Director
4th Aug 20207:00 amRNSFinal high-grade intersections at Longonjo
31st Jul 20204:41 pmRNSSecond Price Monitoring Extn
31st Jul 20204:35 pmRNSPrice Monitoring Extension
31st Jul 20207:00 amRNSQuarterly activities and Cashflow Report
29th Jul 20207:00 amRNSAppointment of London broker SI Capital
27th Jul 20207:00 amRNSAppointment of Paradigm Project Management
20th Jul 20207:00 amRNSEPCF Heads of Agreement for Longonjo Project
13th Jul 20208:23 amRNSFurther high grade drill results at Longonjo
6th Jul 20207:00 amRNSAdmission to Trading on the London Stock Exchange

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.