The latest Investing Matters Podcast episode featuring Jeremy Skillington, CEO of Poolbeg Pharma has just been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksPensana Plc Regulatory News (PRE)

Share Price Information for Pensana Plc (PRE)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 25.50
Bid: 25.00
Ask: 25.90
Change: -1.55 (-5.74%)
Spread: 0.90 (3.60%)
Open: 26.10
High: 26.20
Low: 25.10
Prev. Close: 27.00
PRE Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Operational Update for Saltend and Longonjo

28 Nov 2022 07:00

RNS Number : 6977H
Pensana PLC
28 November 2022
 

28 NOVEMBER 2022

 

 

Pensana Plc

("Pensana" or the "Company")

 

Operational Update for Saltend and Longonjo

 

 

Following the Company's operational update of 26 October 2022, Pensana is pleased to report that Project Delivery Teams for each of the Saltend and Longonjo projects have moved on-site and have commenced the early construction programmes.

Saltend

 

At Saltend, the Company's principal contractor, Wood, is on-site, overseeing Yorkshire Water's nominated contractor for the relocation of existing pipework along the site's western boundary. This is progressing well as part of the activities to enable the main contractual works to commence early in the New Year.

The contracts for the earthworks have been assessed for imminent award, per the construction plan schedule, and are overseen by the Wood, which has been appointed to supervise these contracts alongside Pensana's recently appointed owners' team construction manager, Mark O'Rourke. 

Saltend now has 24/7 site security following the installation of the construction offices, security and welfare cabins and the development of the site access locations.

Longonjo

 

The Longonjo earthworks and civils contractor, Grupo Nov, has mobilised to site. Ground clearing of the area for the main construction camp has been undertaken. The fabrication of the construction camp buildings by Bushtec at their plant in South Africa, is progressing well and is on schedule for delivery to site in January 2023.

Kick-off site sessions were held with the sub-contractors appointed for site electrical reticulation (Electra) and main HT/LT sub-stations (Enerline), who completed their pre-mobilisation site inspections alongside the Pensana owners' team.

Contractors associated with the process water supply (ERM), tailings storage facilities (SRK), and waste management services (AES) have participated as part of the ongoing detailed design development workstreams.

Under the Stakeholder Engagement Program, updates on the Longonjo site activities were presented by Project Director, Kevin Botha, to the Governor of Huambo and the Longonjo Administrator.

Sessions have been held with Port of Lobito operations and local suppliers of construction materials to confirm arrangements for the main construction requirements.

 Environment Social Governance (ESG)

 

Pensana's ESG commitment to ensure direct long-term economic benefit to Longonjo's local communities is progressing well. Demonstration farming plots have been installed on a dedicated area with multiple purposes of livelihood restoration. This has demonstrated increased yields and crop optimisation, providing food security for the Longonjo operations and delivering economic benefit to the region. The demonstration plots also allow Pensana to assess the most successful strategies to increase and enhance the natural habitat, leading to an overall biodiversity net gain.

Operational readiness

 

Recruitment of key operational personnel for both Saltend and Longonjo is continuing. The intention is for key operators to be part of the construction process to assist them moving seamlessly into commissioning.

 

Tim George CEO commented:

 

"Following our previous update in October we are extremely pleased with the progress at both sites. Our early construction management team has continued to grow with the addition of Mark O'Rourke appointed as a construction manager in Saltend. The enabling works appointed last month are on-site delivering to project schedule and making good progress. These critical developments will allow us to move forward quickly in delivering independent and sustainable world-class rare earth facilities at both our operations." 

 

- ENDS -

 

For further information, please contact:

 

Shareholder/analyst enquiries:

Pensana Plc

Paul Atherley, Chairman IR@pensana.co.uk

Tim George, Chief Executive Officer

Rob Kaplan, Chief Financial Officer

George Zacharias, Group Company Secretary

 

Media enquiries:

FGS Global:

Gordon Simpson / Richard Crowley Pensana-LON@fgsglobal.com

 

 

About Pensana Plc

The electrification of motive power is the most important part of the energy transition if we are to tackle climate change and one of the biggest energy transitions in history. Magnet metal rare earths are central to that transition, forming a critical part of the technology for efficient electric vehicle motors and offshore wind turbines.

Pensana plans to establish its Saltend processing hub as an independent and sustainable supplier of the key rare earth magnet metal oxides to a market which is currently dominated by China.

The US$195 million Saltend facility is being designed to produce circa 12,500 tonnes per annum of rare earth products, of which 4,500 tonnes will be neodymium and praseodymium oxide (NdPrO), representing over 5% of the world market in 2025.

Pensana's plug-and-play facility is located within the world-class Saltend Chemicals Park, a cluster of leading chemicals and renewable energy businesses in the Humber Freeport and will create over 500 jobs during construction and over 125 direct jobs once in production.

Powered by low-carbon offshore wind, it will be the first major separation facility to be established in over a decade and will become one of the few major producers located outside China.

Feedstock will be shipped as a clean, high purity mixed rare earth sulphate (MRES) from the Company's Longonjo low-impact operations in Angola. The mine's state-of-the-art concentrator and proprietary MRES processing plant are designed by Wood to the highest international standards.

The operations will be powered by renewable energy from hydroelectric power and connected to the Port of Lobito by the recently upgraded Benguela railway line.

Pensana believes that provenance of critical rare earth materials supply, life cycle analysis and GHG Scope 1, 2 and 3 emissions will all become significant factors in supply chains for major customers.

The Company intends to offer customers an independently and sustainably sourced supply of the metal oxides and carbonates of increasing importance to a range of applications central to addressing the energy transition.

Pensana is also aiming to establish Saltend as an attractive alternative to mining houses that may otherwise be limited to selling their products to China, having designed the facility to be easily adapted to cater for a range of rare earth feedstocks.

www.pensana.co.uk

This information is provided by Reach, the non-regulatory press release distribution service of RNS, part of the London Stock Exchange. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.Reach is a non-regulatory news service. By using this service an issuer is confirming that the information contained within this announcement is of a non-regulatory nature. Reach announcements are identified with an orange label and the word “Reach” in the source column of the News Explorer pages of London Stock Exchange’s website so that they are distinguished from the RNS UK regulatory service. Other vendors subscribing for Reach press releases may use a different method to distinguish Reach announcements from UK regulatory news.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
NRAEDLFLLFLEFBK
Date   Source Headline
19th Apr 20247:00 amPRNUpdate on FSDEA US$15 million loan facility
15th Apr 202410:38 amPRNDirectors Dealings
12th Apr 20244:35 pmPRNHolding(s) in Company
8th Apr 20247:02 amPRNGrant of Share Awards
8th Apr 20247:01 amPRNIssue of Equity
8th Apr 20247:00 amPRNDirectors Dealings
4th Apr 202410:30 amPRNCorrection: Coola Project: Encouraging Sulima West Results
4th Apr 20247:00 amPRNCoola Project: Encouraging Sulima West Results
28th Mar 20241:28 pmPRNUnaudited Interim results for the six months ended 31 December 2023
11th Mar 20247:00 amPRNUpdate on Coola and Sulima West Exploration Programmes
4th Mar 20247:00 amPRNLongonjo Project Update
26th Feb 20247:00 amPRNLongonjo Project Debt Finance
5th Feb 20247:00 amPRNLongonjo mixed rare earth carbonate product quality approval
24th Jan 20247:00 amPRNTechnical Due Diligence Report on Longonjo
15th Jan 20249:09 amPRNFSDEA reviews Longonjo construction progress
15th Jan 20247:00 amPRNFSDEA Board Visit
3rd Jan 20247:00 amPRNLongonjo Update
8th Dec 20232:56 pmPRNReport on Payments to Governments for FY 2023
1st Dec 20232:00 pmPRNAGM - Chairman's Presentation
1st Dec 20231:59 pmPRNResult of AGM
20th Nov 20239:00 amPRNLetter of Intent with Yorkshire Energy Park for Magnet Metal Site
31st Oct 20238:00 amPRNAnnual Financial Report & Notice of AGM
31st Oct 20237:16 amPRNUpdate on Finance for the Longonjo and Saltend Projects
23rd Oct 20237:00 amPRNUK Government Grant Offered for Saltend
16th Oct 20237:00 amPRNMeeting with Minister Nusrat Ghani
20th Sep 20237:00 amPRNPensana and partners win Innovate UK grant to develop a low carbon RE supply chain
14th Sep 20237:00 amPRNMineralogical Results from the Coola Exploration Licence
4th Sep 20237:00 amPRNDirector/PDMR Shareholding
29th Aug 20237:00 amPRNUpdate on Sampling Results from the Coola Exploration Licence
21st Aug 20237:00 amPRNLongonjo Operations Update
31st Jul 20237:00 amPRNDirectors Dealings
21st Jul 20231:27 pmPRNDirectors Dealings
17th Jul 20237:00 amPRNDirectors Dealings
27th Jun 20234:37 pmPRNUpdate on Longonjo Financing and Development
27th Jun 20237:00 amPRNIssue of Equity
28th Apr 20238:20 amPRNMajor shareholders to increase holdings in the Company
1st Dec 202211:45 amRNSResults of Annual General Meeting
1st Dec 202211:45 amRNSAnnual General Meeting - Chairman's Presentation
28th Nov 20227:00 amRNSOperational Update for Saltend and Longonjo
16th Nov 202210:36 amRNSEquity Research and Broker Coverage Reports
14th Nov 20227:00 amRNSExploration Results from Coola Exploration Licence
26th Oct 20227:00 amRNSSaltend and Longonjo Operational Update
18th Oct 20229:00 amRNSInternational Rare Earth Conference Presentation
3rd Oct 20227:00 amRNSPensana signs a MoU for 25% of production
27th Sep 20227:00 amRNSPensana Launches ESG Strategy
20th Sep 20227:00 amRNSPensana and Polestar to create climate-neutral car
2nd Sep 20224:40 pmRNSSecond Price Monitoring Extn
2nd Sep 20224:35 pmRNSPrice Monitoring Extension
1st Sep 20224:35 pmRNSPrice Monitoring Extension
26th Aug 20224:41 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.