Longonjo Project Update

4 Mar 2024 07:00

Pensana Plc - Longonjo Project Update

Pensana Plc - Longonjo Project Update

PR Newswire

LONDON, United Kingdom, March 04

 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION

 

Pensana Plc

 

Long lead items orders placed and site preparation works well underway at Longonjo

 

Pensana (PRE.L) (the Company) is pleased to provide the following update on the Longonjo project:

 

 

Concrete foundations have been poured for the 316-person modular camp manufactured in South Africa for despatch to site later this month.The on-site team, under the leadership of experienced Project Manager Kevin Botha, is continuing to make good progress with preparatory works ahead of main construction anticipated in May 2024, with cold commissioning commencing in August 2025.

 

An order has been placed with NCP International, a global supplier of new and refurbished comminution equipment based in South Africa, for the US$2.3 million ball mill for delivery from Johannesburg to meet the construction and commissioning timelines for the concentrator plant.

 

The detailed design and procurement documentation for other main long lead time or critical path items, such as the thickeners and flotation columns in the concentrator section, along with key equipment in the recovery/MREC section, such as the sulphuric acid plant, have been completed and orders will be placed with the selected vendors shortly.

 

Grupo Nov has completed the civils and services connections for the initial section of the 316-person modular construction camp. The US$1.3 million camp has been fabricated off site and is ready for shipment from Johannesburg to site during March 2024.

 

All the site access roads have been completed within the licence area. The 5,000-litre potable water tank is ready for installation to support the construction camp and the future plant facilities.

 

High priority is being given to community relations and in particular to the resettlement action and livelihoods restoration plans which are progressing according to plan and are being well received.

 

The agricultural demonstration plots are in their second year and continue to generate excellent baseline data. They are providing the opportunity to train local farmers in the latest agricultural methods.

 

The mine and processing plant will be constructed from May 2024 and commissioning of the various circuits will commence in March 2025 and continue until final commissioning in April 2026.

 

A schedule of the expenditures is set out below.

 

Quarterly Expenditures

US Dollars

Activity

May - July 2024

         5 044 000

Civil and Earth Works

August – October 2024

       18 889 000

Structural and Mechanical installation

November – January 2025

       32 435 000

Platework and piping installation

February – April 2025

       36 032 000

Electrical installation

May -July 2025

       36 185 000

Instrumentation installation

August – October 2025

       38 274 000

Cold Commissioning

November – January 2026

       23 096 000

Hot Commissioning

February – April 2026

6 476 000

Final Commissioning

Total

     196 432 000

 

 

Tim George CEO commented: The growing on-site team, supported by experienced contractor Grupo Nov, is fully operational and is well advanced with the earth works and other preparatory works ahead of the commencement of the main civils and earthworks campaigns in the weeks ahead.

 

We are particularly pleased with the attention to health and safety, environmental performance, the training completed on site and the continued focus on the community engagement programs. This will continue to be a priority as we build out the workforce which will increase to over 650 people on site at peak construction later this year.”  

About Longonjo

 

The electrification of motive power through Electric Vehicles and Wind Turbines is the biggest energy transition in history and is forecast to generate a demand growth for magnet metal NdPr of 7.5% CAGR over the next decade.

 

Pensana owns one of the world's largest undeveloped rare earth mines, and one of only three with a JORC Reserve greater than 100,000 tonnes of NdPr.

 

Pensana recently announced that one of its major potential customers has approved the product qualification specifications for Longonjo’s proposed MREC product. The Longonjo MREC contains 50% Total Rare Earth Oxide of which 24% is NdPr with minimal impurities and is radionuclide-free.

 

Longonjo is expected to produce 20,000 tonnes of MREC commencing 2026 and 40,000 tonnes of MREC from 2029 onwards following the planned expansion.

 

At full production Longonjo will produce ~5% of world production of NdPr in the form of an exported mixed rare earth carbonate.

 

The upfront capital cost of US$217 million for the fully permitted mine and processing facilities is amongst the lowest amongst its peers.

 

The information contained within this announcement is considered by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No.596/2014. Upon the publication of this announcement via a Regulatory Information Service, this inside information will be considered to be in the public domain. The person responsible for arranging for the release of this announcement on behalf of the Company is Paul Atherley, Chairman.

 

- ENDS –

 

For further information, please contact:

 

Shareholder/analyst enquiries:

Pensana Plc 

Paul Atherley, Chairman IR@pensana.co.uk

Tim George, Chief Executive Officer

Rob Kaplan, Chief Financial Officer

 

 

 

 

 



Date   Source Headline
8th Jun 20267:00 amPRNUpdate on Longonjo Mine Development, Downstream and Offtake
28th Apr 20264:59 pmPRNHolding(s) in Company
17th Apr 20267:00 amPRNUS$165 million Strategic Investment to support U.S. Mine to Magnet strategy
9th Mar 202611:20 amPRNAdjournment of General Meeting and Corporate Presentation
4th Mar 20267:28 amPRNIncreased US$165 million Strategic Investment to support U.S. Mine to Magnet strategy - Proposed adjournment of General Meeting
3rd Mar 20267:00 amPRNConstruction on track for 2027 first production
10th Feb 20263:10 pmPRNUS$ 160 million Strategic Equity Investment
4th Feb 20267:00 amPRNUpdate on US$25 million Longonjo mine finance
21st Jan 202612:28 pmPRNIssue of Equity
21st Jan 20267:04 amPRNUpdate on Longonjo infill and resource expansion drill programme
14th Jan 202612:28 pmPRNDirectors Dealings
14th Jan 20267:00 amPRNLongonjo Main Construction well underway
23rd Dec 20252:09 pmRNSHolding(s) in Company
23rd Dec 20252:09 pmPRNHolding(s) in Company
19th Dec 202511:08 amRNSIssue of Equity - Updated Admission Date and number of shares to be issued
19th Dec 202511:08 amPRNIssue of Equity - Updated Admission Date and number of shares to be issued
18th Dec 20251:46 pmRNSIssue of Equity
18th Dec 20251:46 pmPRNIssue of Equity
18th Dec 20251:01 pmRNSIssue of Equity
18th Dec 20251:01 pmPRNIssue of Equity
18th Dec 20257:00 amPRNMajor shareholder support for US Strategy
16th Dec 202510:00 amPRNIssue of Equity
15th Dec 20253:15 pmPRNIssue of Equity/Total Voting Rights
9th Dec 20257:00 amPRNUS$100 million Strategic Equity Investment
3rd Dec 202512:08 pmPRNAnnual General Meeting - Chairman's Presentation
3rd Dec 202511:57 amPRNResult of AGM
27th Nov 20257:00 amPRNLongonjo study lifts HREE production fivefold
17th Nov 20257:00 amPRNMajor drill programme to increase Longonjo resource to over one billion tonnes
10th Nov 20257:00 amPRNNotice of Annual General Meeting and Form of Proxy
31st Oct 20258:43 amPRNNew Corporate Presentation
28th Oct 20257:00 amPRNU.S. EXIM debt funding to accelerate U.S. mine-to-magnet supply chain
22nd Oct 20257:00 amPRNPartnership with Vacuumschmelze GmbH to establish mine-to-magnet supply chain in the US
15th Oct 20259:00 amPRNPublication of Annual Report 2025 and Notice of Annual General Meeting
9th Oct 20251:21 pmPRNIssue of Equity
30th Sep 20257:00 amPRNDate of Annual General Meeting and proposed share consolidation
26th Sep 20254:34 pmPRNHolding(s) in Company
25th Sep 20259:15 amPRNNew Corporate Presentation
9th Sep 20257:00 amPRNAppointment of Chief Operating Officer
5th Sep 202511:04 amPRNIssue of Equity
3rd Sep 20254:57 pmPRNHolding(s) in Company
11th Aug 20257:00 amPRNAppointment of US advisor Stonegate Capital Partners
28th Jul 20257:00 amPRNLongonjo construction budget on track and Coola carbonatite drilling
23rd Jun 20257:00 amPRNMOU with ReElement Technologies to develop a sustainable rare earth supply chain
18th Jun 202511:22 amPRNIssue of Equity
18th Jun 20259:17 amPRNHolding(s) in Company
16th Jun 20257:00 amPRNMOU with Toyota Tsusho Corporation for Rare Earth Offtake
13th Jun 20259:59 amPRNHolding(s) in Company
10th Jun 202512:21 pmPRNGrant of Share Awards
10th Jun 202512:19 pmPRNIssue of Equity/Total Voting Rights
5th Jun 202511:10 amPRNIssue of Equity

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.