PROGRESS REPORT

5 Apr 2011 07:00

RNS Number : 2784E
Patagonia Gold PLC
05 April 2011
 



PATAGONIA GOLD PLC

 

  5th April 2011

 

PROGRESS REPORT

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Final preparations for the commissioning of the Lomada Trial Heap leach project are nearing completion. Irrigation for conditioning of the ore pad is scheduled to commence on the 10th April with handover of the commissioned process facility by the construction company, INFA, scheduled for the 25th April.

 

·; Initial results from the recently completed extension and infill drilling campaign on the Lomada deposit are highly encouraging, including drill hole LLD10-17 intersecting 18 metres at 10.95 grams per tonne gold . A Resource and Scoping study upgrade is in progress with completion anticipated in Q2.

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

The first stage of the Lomada project consists of a 50,000 tonne trial heap leach pad and processing facility, which based on 70% recovery, is estimated to yield approximately 2,500 ounces of gold for the first 6 metre loading.

 

Work on the Lomada project commenced in late September 2010. All sections of works are now complete with the exception of the processing facility, the commissioning of which will commence next week, with handover by the construction company, INFA, scheduled for the 25th April.

 

All staff and operators have been hired and are currently undergoing training in the safe use and operation of the facilities and equipment on site. Power generators, fuel and water storage together with other ancillary items have been installed and are in operation. Sufficient reagents and consumables have been purchased for the anticipated life of the Lomada project.

 

Full operation of the Lomada project will commence soon after the commissioning of the processing plant with the first production of gold expected in early May.

 

Updated images of the Lomada project can be viewedon the website, www.patagoniagold.com 

 

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational.

 

Lomada Resource Upgrade:

Patagonia Gold SA (PGSA) has recently completed an extension and infill drilling campaign, comprising 35 diamond drill holes HQ core for 4,441 metres, aimed at enlarging the resource and advancing the inferred part of the resource into an indicated category. Results received to date are highly encouraging and include:

 

Hole No.

From

To

Interval

Grade

metres

metres

metres

Au g/t

LLD-10-01

93.00

99.00

6.00

11.22

including

95.00

97.00

2.00

20.30

LLD-10-03

71.00

85.00

14.00

5.67

LLD-10-14

54.00

74.00

20.00

6.86

including

60.00

67.00

7.00

14.52

LLD-10-15

97.00

112.00

15.00

3.91

including

100.00

105.00

5.00

7.62

LLD-10-17

61.00

79.00

18.00

10.95

including

73.00

78.00

5.00

27.14

LLD-10-24

98.00

107.00

9.00

4.37

 

Table 1: Lomada Project table of significant Intercepts 2010/11 DDH extension and infill.

 

PGSA has retained Mining Engineers, Chlumsky, Armbrust and Meyer, LLC (CAM) of Lakewood, Colorado, to prepare a NI 43-101 report for the upgrade of the resource at Lomada, scheduled for completion in Q2, 2011.

 

The upgraded resource, together with the results from the trial Lomada project, will be used to revise the 2009 Scoping study of the Lomada project prior to the commencement of the main heap leach project.

 

Matthew Boyes, (BSC. Geology, member AusIMM) Development Manager for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSSUFMLFFSESL
Date   Source Headline
26th Nov 20121:00 pmRNSGold Room commissioned and first gold production
22nd Nov 20127:00 amRNSLomada de Leiva Permit
25th Oct 20126:15 pmRNSPlacing and Subscription
17th Oct 201212:31 pmRNSUpdate: Lomada de Leiva
21st Sep 20124:40 pmRNSSecond Price Monitoring Extn
21st Sep 20124:35 pmRNSPrice Monitoring Extension
17th Sep 20127:00 amRNSHalf Yearly Report
10th Sep 20127:00 amRNSCap-Oeste Resource Update
4th Sep 20124:35 pmRNSPrice Monitoring Extension
20th Aug 20124:35 pmRNSPrice Monitoring Extension
31st Jul 20124:35 pmRNSPrice Monitoring Extension
13th Jul 20124:40 pmRNSSecond Price Monitoring Extn
13th Jul 20124:35 pmRNSPrice Monitoring Extension
9th Jul 20124:35 pmRNSPrice Monitoring Extension
5th Jul 20127:00 amRNSDrilling Report
2nd Jul 20124:35 pmRNSPrice Monitoring Extension
28th Jun 20121:00 pmRNSDirector Shareholding
6th Jun 20125:45 pmRNSResult of AGM
6th Jun 20127:00 amRNSPlacing and Subscription
1st Jun 20127:00 amRNSExercise of Options
30th May 201211:44 amRNSReplacement - Operations Update: Lomada de Leiva
30th May 20127:00 amRNSOperations Update - Lomada de Leiva Gold Project
29th May 20127:00 amRNSExercise of Options
25th May 20127:00 amRNSExercise of Options
14th May 20129:38 amRNSPosting of Annual Report and Notice of AGM
25th Apr 20127:00 amRNS2011 Year End Financial Results
28th Mar 20127:00 amRNSDrilling Update - Cap-Oeste
16th Mar 20124:35 pmRNSPrice Monitoring Extension
14th Mar 20127:00 amRNSExercise of Options
7th Mar 20127:00 amRNSDirector Shareholding
6th Mar 20121:30 pmRNSExercise of Options
21st Feb 20127:00 amRNSCap-Oeste Metallurgical Test Update
20th Feb 20127:00 amRNSGrant of Options
18th Jan 201212:30 pmRNSDirector/PDMR Shareholding
12th Jan 20127:00 amRNSCap-Oeste Drilling Update
5th Jan 20127:00 amRNSACQUISITION OF ESTANCIA 'EL TRANQUILO'
20th Dec 20117:00 amRNSExercise of Options
14th Dec 20117:00 amRNSAppointment of Broker
7th Dec 201112:00 pmRNSCommencement of trading on TSX
6th Dec 20117:00 amRNSDual Listing on TSX
2nd Dec 20117:00 amRNSDirectorate Change
30th Nov 20117:00 amRNSCAP-OESTE UPDATED RESOURCE ESTIMATE
14th Nov 20117:00 amRNSChange of Registrar
3rd Nov 201111:38 amRNSDirector Declaration
2nd Nov 20117:00 amRNSDirectorate Change
31st Oct 20117:00 amRNSProgress Update - COSE
26th Oct 20117:00 amRNSFOMICRUZ SHAREHOLDERS AGREEMENT
24th Oct 20117:00 amRNSDrilling Report
3rd Oct 20113:01 pmRNSIssue of Equity
28th Sep 20117:00 amRNSInterim Statement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.