PROGRESS REPORT

5 Apr 2011 07:00

RNS Number : 2784E
Patagonia Gold PLC
05 April 2011
 



PATAGONIA GOLD PLC

 

  5th April 2011

 

PROGRESS REPORT

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Final preparations for the commissioning of the Lomada Trial Heap leach project are nearing completion. Irrigation for conditioning of the ore pad is scheduled to commence on the 10th April with handover of the commissioned process facility by the construction company, INFA, scheduled for the 25th April.

 

·; Initial results from the recently completed extension and infill drilling campaign on the Lomada deposit are highly encouraging, including drill hole LLD10-17 intersecting 18 metres at 10.95 grams per tonne gold . A Resource and Scoping study upgrade is in progress with completion anticipated in Q2.

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

The first stage of the Lomada project consists of a 50,000 tonne trial heap leach pad and processing facility, which based on 70% recovery, is estimated to yield approximately 2,500 ounces of gold for the first 6 metre loading.

 

Work on the Lomada project commenced in late September 2010. All sections of works are now complete with the exception of the processing facility, the commissioning of which will commence next week, with handover by the construction company, INFA, scheduled for the 25th April.

 

All staff and operators have been hired and are currently undergoing training in the safe use and operation of the facilities and equipment on site. Power generators, fuel and water storage together with other ancillary items have been installed and are in operation. Sufficient reagents and consumables have been purchased for the anticipated life of the Lomada project.

 

Full operation of the Lomada project will commence soon after the commissioning of the processing plant with the first production of gold expected in early May.

 

Updated images of the Lomada project can be viewedon the website, www.patagoniagold.com 

 

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational.

 

Lomada Resource Upgrade:

Patagonia Gold SA (PGSA) has recently completed an extension and infill drilling campaign, comprising 35 diamond drill holes HQ core for 4,441 metres, aimed at enlarging the resource and advancing the inferred part of the resource into an indicated category. Results received to date are highly encouraging and include:

 

Hole No.

From

To

Interval

Grade

metres

metres

metres

Au g/t

LLD-10-01

93.00

99.00

6.00

11.22

including

95.00

97.00

2.00

20.30

LLD-10-03

71.00

85.00

14.00

5.67

LLD-10-14

54.00

74.00

20.00

6.86

including

60.00

67.00

7.00

14.52

LLD-10-15

97.00

112.00

15.00

3.91

including

100.00

105.00

5.00

7.62

LLD-10-17

61.00

79.00

18.00

10.95

including

73.00

78.00

5.00

27.14

LLD-10-24

98.00

107.00

9.00

4.37

 

Table 1: Lomada Project table of significant Intercepts 2010/11 DDH extension and infill.

 

PGSA has retained Mining Engineers, Chlumsky, Armbrust and Meyer, LLC (CAM) of Lakewood, Colorado, to prepare a NI 43-101 report for the upgrade of the resource at Lomada, scheduled for completion in Q2, 2011.

 

The upgraded resource, together with the results from the trial Lomada project, will be used to revise the 2009 Scoping study of the Lomada project prior to the commencement of the main heap leach project.

 

Matthew Boyes, (BSC. Geology, member AusIMM) Development Manager for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSSUFMLFFSESL
Date   Source Headline
30th Mar 20157:00 amRNSOperational Update
19th Mar 20157:00 amRNSUpdate on Cap-Oeste
3rd Mar 20154:40 pmRNSSecond Price Monitoring Extn
3rd Mar 20154:35 pmRNSPrice Monitoring Extension
18th Feb 20154:40 pmRNSSecond Price Monitoring Extn
18th Feb 20154:35 pmRNSPrice Monitoring Extension
16th Feb 201512:00 pmRNSHolding(s) in Company
5th Feb 201511:54 amRNSAdditional Listing
3rd Feb 20157:00 amRNSLomada Production Results
6th Jan 20152:44 pmRNSDirector/PDMR Shareholding
5th Jan 20153:30 pmRNSHolding(s) in Company
22nd Dec 201410:45 amRNSCompany Update
18th Dec 201411:44 amRNSHolding(s) in Company
8th Dec 20141:00 pmRNSResult of Fundraising and General Meeting
18th Nov 20147:00 amRNSSubscription and Open Offer
11th Nov 20147:00 amRNSOperational Update
26th Sep 20147:00 amRNSInterim Results
11th Sep 20147:00 amRNSOperational Update
3rd Sep 20142:56 pmRNSResignation of Director
3rd Sep 201412:38 pmRNSDirector/PDMR Shareholding - Replacement
2nd Sep 20144:09 pmRNSDirector/PDMR Shareholding
14th Aug 20147:00 amRNSChange of Broker
28th Jul 20147:00 amRNSGrant of Options
25th Jun 20143:14 pmRNSResult of AGM
19th May 20147:00 amRNSFinal Results
4th Apr 20147:00 amRNSCorporate Presentation
26th Feb 20142:00 pmRNSDirectors' Shareholdings/Issue of equity
18th Feb 20149:50 amRNSExercise of Options
14th Feb 20147:00 amRNSExercise of Options
29th Jan 20147:00 amRNSOperational Update
23rd Jan 20143:15 pmRNSExercise of Options and Director Shareholding
13th Jan 20143:20 pmRNSHolding(s) in Company
9th Dec 20134:35 pmRNSPrice Monitoring Extension
18th Nov 20137:00 amRNSOperational Update
29th Oct 20134:02 pmRNSHolding(s) in Company
28th Oct 20134:40 pmRNSSecond Price Monitoring Extn
28th Oct 20134:35 pmRNSPrice Monitoring Extension
11th Oct 20133:13 pmRNSHolding(s) in Company
4th Oct 201310:15 amRNSExercise of Options
4th Oct 201310:15 amRNSGrant of Options
24th Sep 201311:30 amRNSDirectors' Dealings
20th Sep 20134:40 pmRNSSecond Price Monitoring Extn
20th Sep 20134:35 pmRNSPrice Monitoring Extension
20th Sep 20132:50 pmRNSGrant of Options
12th Sep 20137:00 amRNSHalf Yearly Report
9th Sep 20134:40 pmRNSSecond Price Monitoring Extn
9th Sep 20134:35 pmRNSPrice Monitoring Extension
5th Sep 20137:00 amRNSUpdate: La Manchuria and Lomada de Leiva
4th Sep 20134:35 pmRNSPrice Monitoring Extension
3rd Sep 20134:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.